6838-6838 1/2 N AURA AVE 91335

Certificate Information: 6838-6838 1/2 N AURA AVE 91335

Application / Permit
22014-20000-01622
Plan Check / Job No.
B22VN05320
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(ePlan) 1ST FLOOR EXISTING GARAGE CONVERSION TO (N) ACCESSORY DWELLING UNIT WITH ADDITIONAL FLOOR AREA INCLUDING (N) 2-CAR GARAGE PER LAMC 12.22A.33.(c)-(d) AND ADD SINGLE FAMILY DWELLING ON 2ND FLOOR PER SB9. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 11/29/2022
Issuing Office
Current Status
CofO Corrected on 4/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 YOUNG KIM
Corrections Issued 5/16/2022 YOUNG KIM
Quality Review Completed 6/2/2022 FARUK SEZER
Applicant returned to address corrections 8/8/2022 YOUNG KIM
Applicant returned to address corrections 8/11/2022 YOUNG KIM
Applicant returned to address corrections 9/7/2022 YOUNG KIM
Applicant returned to address corrections 9/8/2022 YOUNG KIM
Applicant returned to address corrections 10/18/2022 YOUNG KIM
Applicant returned to address corrections 11/10/2022 YOUNG KIM
Plan Check Approved 11/28/2022 YOUNG KIM
Issued 11/29/2022 APPLICANT
CofO in Progress 1/31/2024 JEFFREY BULL
CofO Issued-Status Void 4/17/2024 DANIEL ORRANTE
Permit Finaled-Status Void 4/17/2024 DANIEL ORRANTE
Re-Activate Permit 4/25/2024 JOHN JANSON
No Progress 1/13/2025 SEAN WIRCH
CofO in Progress 1/13/2025 SEAN WIRCH
Re-Activate Permit 4/16/2025 JOHN JANSON
CofO Corrected-Status Void 4/16/2025 JOHN JANSON
Permit Finaled-Status Void 4/16/2025 JOHN JANSON
Permit Finaled 4/16/2025 JOHN JANSON
CofO Corrected 4/16/2025 JOHN JANSON
Permit Finaled 4/16/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/9/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 6/9/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/21/2022 JOSE DUARTE-DIAZ
ZI Cleared 6/22/2022 STEVEN WECHSLER
Construction near power lines Cleared 6/26/2022 PATRICK MAGALLANES
Senate Bill 9 Cleared 9/23/2022 NATHAN ROMINE
Address approval Cleared 10/11/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Xia,, Ji; Lic. No.: C89014 420 S MADISON AVE   APT 301    PASADENA, CA 91101

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/6/2023 Approved JEFFREY BULL
Sewer 2/22/2023 Approved JEFFREY BULL
Underground Mechanical 2/22/2023 Approved JEFFREY BULL
Excavation/Setback/Form/Re-Bar 4/6/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 4/6/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 6/2/2023 Corrections Issued JEFFREY BULL
Green Building Rough 6/2/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 6/6/2023 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 6/6/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 6/6/2023 Not Ready for Inspection JEFFREY BULL
Structural Steel Frame 6/6/2023 Not Ready for Inspection JEFFREY BULL
Wood Frame 6/6/2023 Partial Approval JEFFREY BULL
Deputy Wood Construction 6/9/2023 Conditional Approval JEFFREY BULL
Underground Mechanical 7/28/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 8/7/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 8/7/2023 Corrections Issued VINCENT HANLEY
Green Building Rough 8/7/2023 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 8/7/2023 Not Ready for Inspection VINCENT HANLEY
Insulation 8/7/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 8/7/2023 Not Ready for Inspection VINCENT HANLEY
Wood Frame 8/7/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 8/14/2023 Corrections Issued JEFFREY BULL
ELECTRICAL-Rough 8/14/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 8/14/2023 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 8/14/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 8/14/2023 Not Ready for Inspection JEFFREY BULL
Wood Frame 8/14/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 8/16/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Approved JEFFREY BULL
HVAC-Rough 8/16/2023 Approved JEFFREY BULL
PLUMBING-Rough 8/16/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 8/22/2023 Approved JEFFREY BULL
Green Building Rough 8/22/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 8/22/2023 Approved JEFFREY BULL
Insulation 8/29/2023 Approved JEFFREY BULL
Drywall Nailing 9/13/2023 Approved JEFFREY BULL
Shower Pan 10/2/2023 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 12/6/2023 Approved JEFFREY BULL
Final 12/6/2023 Corrections Issued JEFFREY BULL
Gas Test 12/6/2023 Approved JEFFREY BULL
HVAC-Final 12/6/2023 Not Ready for Inspection JEFFREY BULL
Service/Power Release 12/6/2023 Approved JEFFREY BULL
Smoke Detectors 12/6/2023 Approved JEFFREY BULL
Final 1/31/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 1/31/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Approved JEFFREY BULL
Special/Order Compliance 4/25/2024 Corrections Issued JEFFREY BULL