13941 W PEACH GROVE ST 91423
Certificate Information: 13941 W PEACH GROVE ST 91423
- Application / Permit
- 22014-20000-01610
- Plan Check / Job No.
- B22VN05284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE ONE STORY ADDITION AND MAJOR REMODEL TO (E) SFD _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D (SEE COMMENTS).
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | DAWN MC NULTY |
| Corrections Issued | 5/9/2022 | DAWN MC NULTY |
| Quality Review Completed | 5/16/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Applicant returned to address corrections | 6/29/2022 | DAWN MC NULTY |
| Plan Check Approved | 7/20/2022 | DAWN MC NULTY |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 12/3/2024 | MISAEL ESPARZA |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 5/20/2022 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/28/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 7/7/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/8/2022 | CHRIS CHAHBAZ |
| Public Works-Highway Ded. | Cleared | 7/19/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 7/19/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Yd Construction & Development Inc; Lic. No.: 839200-B | 15030 VENTURA BLVD #216 SHERMAN OAKS, CA 91403 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/22/2022 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/2/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/28/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/14/2022 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 11/14/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/14/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/28/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 12/12/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 12/12/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 12/21/2022 | Approved | MISAEL ESPARZA |
| Gas Test | 12/21/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 12/21/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 12/21/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/30/2022 | Approved | MISAEL ESPARZA |
| Gas Test | 12/30/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/30/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/5/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/5/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/5/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 1/5/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/11/2023 | Approved | MISAEL ESPARZA |
| Wood Frame | 1/11/2023 | Approved | MISAEL ESPARZA |
| Insulation | 1/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 2/13/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/17/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 6/26/2023 | Approved | THOMAS FINNILA |
| Final | 12/27/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/27/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 12/27/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/27/2023 | Approved | MISAEL ESPARZA |
| Final | 2/27/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/2/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 12/20/2024 | Approved | MISAEL ESPARZA |