17354 W CALIFA ST 91316

Certificate Information: 17354 W CALIFA ST 91316

Application / Permit
22014-20000-01605
Plan Check / Job No.
B22VN05270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-10" X 13'-0" IRREGULAR SHAPED ADDITION AND INTERIOR REMODEL TO THE (E) SFD.
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
Issued on 5/6/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/7/2022 APPLICANT
Assigned to Plan Check Engineer 4/13/2022 ARTIN ZARUKIAN
Corrections Issued 4/18/2022 ARTIN ZARUKIAN
Applicant returned to address corrections 4/29/2022 ARTIN ZARUKIAN
Plan Check Approved 5/6/2022 ARTIN ZARUKIAN
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/10/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/20/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor B M K Remodeling Inc; Lic. No.: 1049328-B 15720 VENTURA BLVD #119      ENCINO, CA 91436

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/23/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 5/23/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 5/23/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/6/2022 Partial Approval SEAN HAUPT
Green Building Rough 6/6/2022 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 7/25/2022 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 7/25/2022 Not Ready for Inspection SEAN HAUPT
Final 7/25/2022 Not Ready for Inspection SEAN HAUPT
Green Building Final 7/25/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 7/25/2022 Not Ready for Inspection SEAN HAUPT
Rough-Elec/Plmb/HVAC 7/25/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready SEAN HAUPT
BUILDING-Rough-Frame 8/8/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 8/8/2022 Not Ready for Inspection DAVID SANDOVAL
Insulation 8/8/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 8/8/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 8/16/2022 Approved SEAN HAUPT
Green Building Rough 8/16/2022 Approved SEAN HAUPT
Insulation 8/16/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 8/16/2022 Approved SEAN HAUPT
Drywall Nailing 8/26/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Not Ready SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Not Ready SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Not Ready SEAN HAUPT
Final 1/31/2023 Corrections Issued SEAN HAUPT
Green Building Final 1/31/2023 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 1/31/2023 Not Ready for Inspection SEAN HAUPT