6545-6547 W 84TH PL 90045
Certificate Information: 6545-6547 W 84TH PL 90045
- Application / Permit
- 22014-20000-01601
- Plan Check / Job No.
- B22VN05266
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (37'-2"-26'-5"), ADDITION TO 1ST FLOOR (605 SQFT) OF (E) SFD, AND NEW 2ND FLOOR (449 SQFT) OF AN ADU ADDITION PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 10/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | PETER MOSESIAN |
| Corrections Issued | 5/20/2022 | PETER MOSESIAN |
| Quality Review Completed | 6/3/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Plan Check Approved | 10/7/2022 | PETER MOSESIAN |
| Issued | 10/21/2022 | APPLICANT |
| CofO in Progress | 2/10/2025 | MICHAEL ALLEN |
| CofO Issued | 2/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/28/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | JENSON LEE |
| Sewer availability | Cleared | 7/25/2022 | JENSON LEE |
| Low Impact Development | Cleared | 8/2/2022 | SUNG JOON WON |
| Address approval | Cleared | 8/10/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 8/26/2022 | JENSON LEE |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2022 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 12/16/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 12/20/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/25/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 1/25/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/14/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 4/14/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 4/14/2023 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 4/14/2023 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 4/19/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/24/2023 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 4/27/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 4/27/2023 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 4/27/2023 | Partial Inspection | JESUS PINEDA |
| Deputy Wood Construction | 4/28/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 5/18/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 5/18/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/23/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 5/23/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 5/23/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 5/23/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 5/23/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/26/2023 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 5/26/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 5/26/2023 | Approved | HERBERT GIRON |
| Insulation | 5/26/2023 | Conditional Approval | HERBERT GIRON |
| Special/Order Compliance | 5/26/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 6/2/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 6/9/2023 | Approved | KENNETH NAGLE |
| Sewer | 6/13/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/5/2023 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 9/5/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 7/5/2024 | Approved | JESUS PINEDA |
| Final | 7/5/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 7/5/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 7/5/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 11/14/2024 | Approved | MICHAEL ALLEN |
| Final | 11/14/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Final | 11/14/2024 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 11/14/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 11/14/2024 | Approved | MICHAEL ALLEN |
| Final | 2/7/2025 | OK to Issue CofO | MICHAEL ALLEN |
| Green Building Final | 2/7/2025 | Approved | MICHAEL ALLEN |