15113 W TUBA ST 91345

Certificate Information: 15113 W TUBA ST 91345

Application / Permit
22014-20000-01565
Plan Check / Job No.
B22VN05144
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. 20' x 19' GARAGE AND ADD 14' x 19' FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/7/2022
Issuing Office
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 4/8/2022 JEFFREY TANGONAN
Corrections Issued 4/9/2022 JEFFREY TANGONAN
Building Plans Picked Up 4/15/2022 APPLICANT
Plan Check Approved 5/25/2022 JEFFREY TANGONAN
Issued 6/7/2022 APPLICANT
CofO in Progress 3/9/2023 JENNIFER RABUCHIN
Permit Finaled 3/29/2023 MICHAEL SMITH
CofO Issued 3/29/2023 MICHAEL SMITH
Permit Finaled 3/29/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/21/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CARLOS AGUILERA
Hold Cleared 4/21/2022 JAZELLE A TRINIDAD
Roof/Waste drainage to street Cleared 4/21/2022 CARLOS AGUILERA
Sewer availability Cleared 4/21/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/25/2022 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/2/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 9/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 10/21/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/21/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 11/8/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/8/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 11/8/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/8/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/15/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/15/2022 Approved JENNIFER RABUCHIN
Green Building Rough 11/15/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 11/15/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/15/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 11/15/2022 Approved JENNIFER RABUCHIN
Insulation 11/22/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 11/28/2022 Approved JENNIFER RABUCHIN
Shower Pan 12/20/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/23/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/28/2023 Corrections Issued JENNIFER RABUCHIN
Final 2/28/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 2/28/2023 Approved JENNIFER RABUCHIN
HVAC-Final 2/28/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/28/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/28/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/8/2023 Approved JENNIFER RABUCHIN
Final 3/8/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/8/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/8/2023 Approved JENNIFER RABUCHIN