2319 S MANSFIELD AVE 90016
Certificate Information: 2319 S MANSFIELD AVE 90016
- Application / Permit
- 22014-20000-01562
- Plan Check / Job No.
- B22VN05134
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 14.5' x 17.42' TO THE (E) SINGLE-FAMILY DWELLING, AND AN INTERIOR ALTERATION TO CONVERT A UTILITY ROOM INTO A FULL BATHROOM AND TO REMODEL THE KITCHEN.
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 1/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2022 | LUIS RINCON |
| Corrections Issued | 4/6/2022 | LUIS RINCON |
| Applicant returned to address corrections | 4/26/2022 | LUIS RINCON |
| Plan Check Approved | 5/10/2022 | LUIS RINCON |
| Plan Check Approved | 5/11/2022 | LUIS RINCON |
| Issued | 5/16/2022 | APPLICANT |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| CofO in Progress | 1/19/2024 | JUSTIN HAWLEY |
| Permit Finaled | 1/28/2024 | DEROLD HAUFF |
| CofO Issued | 1/28/2024 | DEROLD HAUFF |
| Permit Finaled | 1/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/13/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | T & N Remodeling Inc; Lic. No.: 1063782-B | 16200 VENTURA BLVD STE 424 ENCINO, CA 91436 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/2/2022 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 6/3/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/30/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 6/30/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 6/30/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 7/15/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 7/19/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/20/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 8/29/2022 | No Access for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 9/9/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 9/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 9/9/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/9/2022 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Rough | 9/9/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 9/9/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 9/22/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/22/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 9/28/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 9/28/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/14/2022 | Approved | STUART CHAPMAN |
| Final | 12/12/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/12/2022 | Approved | STUART CHAPMAN |
| Green Building Final | 12/12/2022 | Approved | STUART CHAPMAN |
| MERV13>=Final | 12/12/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 12/12/2022 | Approved | STUART CHAPMAN |
| Final | 10/6/2023 | Corrections Issued | CALEB MEISTER |
| Final | 11/15/2023 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Final | 1/19/2024 | Approved | JUSTIN HAWLEY |
| Final | 1/19/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 1/19/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 1/19/2024 | Approved | JUSTIN HAWLEY |