17506 W MAYERLING ST 91344

Certificate Information: 17506 W MAYERLING ST 91344

Application / Permit
22014-20000-01560
Plan Check / Job No.
B22VN05124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-5" X 33'-8" ADDITION TO (E) SFD, ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/1/2022
Issuing Office
Valley
Current Status
Issued on 8/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/22/2022 ARTIN ZARUKIAN
Corrections Issued 4/25/2022 ARTIN ZARUKIAN
Building Plans Picked Up 4/25/2022 APPLICANT
Issued 8/1/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/23/2022 ARTIN ZARUKIAN
Sewer availability Cleared 4/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/26/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/9/2022 CARLOS AGUILERA
Miscellaneous Cleared 7/7/2022 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/16/2026   

Inspection Request History

Underground Mechanical 8/8/2022 Approved KRISTEN CAUSEY
Deputy Drilled-In Anchors 8/15/2022 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 8/15/2022 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 8/15/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 12/5/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/10/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 7/10/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Approved STEVEN BACK
Green Building Rough 7/10/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 9/29/2023 Approved STEVEN BACK
Green Building Rough 9/29/2023 Approved STEVEN BACK
HVAC-Rough 9/29/2023 Approved STEVEN BACK
PLUMBING-Rough 9/29/2023 Approved STEVEN BACK
Pre-Inspection 9/29/2023 Partial Inspection STEVEN BACK
BUILDING-Rough-Frame 11/15/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 11/15/2023 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 11/21/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 11/28/2023 Approved STEVEN BACK
Rough-Elec/Plmb/HVAC 11/28/2023 Approved STEVEN BACK
Insulation 12/11/2023 Approved JEFFREY PARD
Drywall Nailing 12/18/2023 No Access for Inspection HENRY KIM
Interior/Exterior Lathing 1/3/2024 Approved STEVEN BACK
Shower Pan 1/3/2024 Approved STEVEN BACK
Special/Order Compliance 6/3/2024 Corrections Issued STEVEN BACK
Drywall Nailing 7/10/2024 Approved STEVEN BACK
Final 4/3/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready STEVEN BACK
Smoke Detectors 4/3/2025 Not Ready for Inspection STEVEN BACK
Special/Order Compliance 4/3/2025 Corrections Issued STEVEN BACK
Final 4/16/2025 Not Ready for Inspection DAVID SCANTLIN
Gas Test 4/16/2025 Approved DAVID SCANTLIN
Green Building Final 4/16/2025 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 4/16/2025 Approved DAVID SCANTLIN
Final 2/3/2026 Not Ready for Inspection JEFFREY PARD
Green Building Final 2/3/2026 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved JEFFREY PARD
Final 6/10/2026 Corrections Issued STEVEN BACK
Green Building Final 6/10/2026 Approved STEVEN BACK