11502 W MORRISON ST 91601

Certificate Information: 11502 W MORRISON ST 91601

Application / Permit
22014-20000-01554
Plan Check / Job No.
B22VN05088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO NEW ADU WITH ADDITION TO REAR OF GARAGE, NEW ATTIC AREA PER LAMC 12.22 A.33(c)-(d) ; FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 10/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 MOHAMMAD ESMAILI
Corrections Issued 4/21/2022 MOHAMMAD ESMAILI
Quality Review Completed 4/22/2022 OMID HEDAYAT
Building Plans Picked Up 4/25/2022 APPLICANT
Applicant returned to address corrections 5/11/2022 MOHAMMAD ESMAILI
Plan Check Approved 10/26/2022 MOHAMMAD ESMAILI
Issued 10/26/2022 APPLICANT
CofO in Progress 4/13/2023 JACK KARGODORIAN
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/13/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/13/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/13/2022 DAGOVERTO GUERRERO
Specific Plan Cleared 5/31/2022 CORREY KITCHENS
ZI Cleared 5/31/2022 CORREY KITCHENS
ZI Cleared 5/31/2022 CORREY KITCHENS
Low Impact Development Cleared 6/30/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/1/2022 JOHN LIN
Construction near power lines Cleared 10/17/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Taewon; Lic. No.: C80632 2320 SANTA CRUZ CT      TORRANCE, CA 90501

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 11/2/2022 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 11/4/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 11/4/2022 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 11/23/2022 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/5/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 12/6/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 12/6/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/7/2022 Approved JACK KARGODORIAN
Green Building Rough 12/7/2022 Approved JACK KARGODORIAN
MERV13>=Rough 12/7/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/14/2022 Not Ready for Inspection JOHN COLEMAN
Sewer 12/14/2022 Approved JOHN COLEMAN
Shower Pan 12/14/2022 Approved JOHN COLEMAN
Insulation 12/19/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/19/2022 Partial Approval JACK KARGODORIAN
Drywall Nailing 12/23/2022 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 12/28/2022 Approved JOHN COLEMAN
ELECTRICAL-Final 3/7/2023 Corrections Issued JACK KARGODORIAN
Gas Test 3/24/2023 Approved JACK KARGODORIAN
Grading Pre-Inspection 3/24/2023 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 3/28/2023 Approved JACK KARGODORIAN
HVAC-Final 3/28/2023 Approved JACK KARGODORIAN
PLUMBING-Final 3/28/2023 Approved JACK KARGODORIAN
Final 4/12/2023 OK to Issue CofO JACK KARGODORIAN
Green Building Final 4/12/2023 Approved JACK KARGODORIAN
MERV13>=Final 4/12/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 4/12/2023 Approved JACK KARGODORIAN