11504 W MORRISON ST 91601
Certificate Information: 11504 W MORRISON ST 91601
- Application / Permit
- 22014-20000-01553
- Plan Check / Job No.
- B22VN05088
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) 1 STORY AND TO TURN (E) ATTIC TO 2ND STORY ADDITION ; FIRE SPRINKLER NFPA 13D
- Permit Issued
- Issued on 7/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/21/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/22/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Applicant returned to address corrections | 5/11/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/19/2022 | MOHAMMAD ESMAILI |
| Issued | 7/29/2022 | APPLICANT |
| CofO in Progress | 4/13/2023 | JACK KARGODORIAN |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/13/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 5/31/2022 | CORREY KITCHENS |
| ZI | Cleared | 5/31/2022 | CORREY KITCHENS |
| ZI | Cleared | 5/31/2022 | CORREY KITCHENS |
| Low Impact Development | Cleared | 6/30/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/1/2022 | JOHN LIN |
Contact Information
| Contractor | Precision Construction Co; Lic. No.: 796588-B | 5709 CALVIN AVENUE TARZANA, CA 91356 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2320 SANTA CRUZ CT TORRANCE, CA 90501 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/23/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/29/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 9/9/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Conditional Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/5/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 12/6/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 12/6/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 12/6/2022 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 12/6/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 12/7/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 12/7/2022 | Approved | JACK KARGODORIAN |
| Insulation | 12/15/2022 | Approved | JOHN COLEMAN |
| Sewer | 12/15/2022 | Approved | JOHN COLEMAN |
| Shower Pan | 12/15/2022 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 12/19/2022 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 12/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 12/28/2022 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 3/7/2023 | Corrections Issued | JACK KARGODORIAN |
| Gas Test | 3/24/2023 | Approved | JACK KARGODORIAN |
| Grading Pre-Inspection | 3/24/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 3/24/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/28/2023 | Approved | JACK KARGODORIAN |
| Gas Test | 3/28/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 3/28/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/28/2023 | Approved | JACK KARGODORIAN |
| Final | 4/12/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/12/2023 | Approved | JACK KARGODORIAN |
| Green Building Final | 4/12/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 4/12/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | JACK KARGODORIAN |