1842 S SHENANDOAH ST 90035
Certificate Information: 1842 S SHENANDOAH ST 90035
- Application / Permit
- 22014-20000-01523
- Plan Check / Job No.
- B22VN04985
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND 45'6-1/4"X14'7-1/4" IRREGULAR SHAPED ADDITION TO THE EXISTING 1-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | COLIN LOREDO |
| Corrections Issued | 5/5/2022 | COLIN LOREDO |
| Quality Review Completed | 5/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| Applicant returned to address corrections | 1/20/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 2/3/2023 | MARVEL DELACRUZ |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 7/19/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 7/23/2024 | DANIEL ORRANTE |
| CofO Issued | 7/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/9/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/10/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 1/4/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Barrier | 5/24/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 5/24/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 6/13/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 6/26/2023 | Partial Approval | JEREMY TODD |
| Green Building Rough | 6/26/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Rough | 6/26/2023 | Partial Approval | JEREMY TODD |
| BUILDING-Rough-Frame | 7/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 7/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/6/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/1/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/26/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 9/26/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/26/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | BEN MOLSTAD |
| Green Building Rough | 9/28/2023 | Approved | BEN MOLSTAD |
| METHANE-Rough | 9/28/2023 | Approved | BEN MOLSTAD |
| Wood Frame | 9/28/2023 | Approved | BEN MOLSTAD |
| Insulation | 10/18/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 10/18/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Shower Pan | 10/18/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 10/31/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 12/6/2023 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 12/6/2023 | Conditional Approval | MEL KHACHATOURIAN |
| Gas Test | 12/8/2023 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 7/11/2024 | Approved | MEL KHACHATOURIAN |
| Final | 7/11/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 7/11/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 7/11/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 7/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 7/11/2024 | Approved | MEL KHACHATOURIAN |
| Final | 7/18/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | MEL KHACHATOURIAN |