13747 W BRACKEN ST 91331

Certificate Information: 13747 W BRACKEN ST 91331

Application / Permit
22014-20000-01520
Plan Check / Job No.
B22VN04978
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. 2-CAR GARAGE (342 SF) W/ 1ST & 2ND STORY ADDITIONS (706 SF) TO ADU 1048 SF PER LAMC 12.22 A.33 (C) & (D).
Permit Issued
Issued on 11/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 CHUNG-WEN CHUANG
Corrections Issued 4/25/2022 CHUNG-WEN CHUANG
Quality Review Completed 5/3/2022 SAI KHUM
Building Plans Picked Up 5/11/2022 APPLICANT
Plan Check Approved 11/8/2022 CHUNG-WEN CHUANG
Issued 11/9/2022 APPLICANT
CofO in Progress 4/20/2023 GREGG CUMMINGS
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/14/2022 CARLOS AGUILERA
Sewer availability Cleared 6/14/2022 CARLOS AGUILERA
Low Impact Development Cleared 8/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/4/2022 CARLOS AGUILERA
Construction near power lines Cleared 9/21/2022 WALTER RAMIREZ
Construction within easement Cleared 9/21/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 12/9/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/13/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 12/16/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Partial Approval GREGG CUMMINGS
Deputy Wood Construction 1/4/2023 Conditional Approval DAVID MATSON
HVAC-Rough 1/17/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 1/17/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 1/18/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 1/18/2023 Corrections Issued GREGG CUMMINGS
Green Building Rough 1/18/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 1/23/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 1/23/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 1/26/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/26/2023 Partial Approval GREGG CUMMINGS
Shower Pan 1/26/2023 Corrections Issued GREGG CUMMINGS
Drywall Nailing 1/30/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/30/2023 Partial Approval GREGG CUMMINGS
Shower Pan 1/30/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 2/3/2023 Partial Inspection MICHEL ABAJAN
Shower Pan 2/3/2023 Approved MICHEL ABAJAN
Underground Mechanical 2/3/2023 Partial Approval MICHEL ABAJAN
Sewer 2/7/2023 Approved GREGG CUMMINGS
Underground Mechanical 2/7/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 3/9/2023 Not Ready for Inspection GREGG CUMMINGS
Final 3/9/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 3/9/2023 Approved GREGG CUMMINGS
HVAC-Final 3/9/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 3/9/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 3/9/2023 Approved GREGG CUMMINGS
Final 4/7/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Final 4/20/2023 Approved GREGG CUMMINGS
Final 4/20/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/20/2023 Approved GREGG CUMMINGS
PLUMBING-Final 4/20/2023 Approved GREGG CUMMINGS