5921 N FALLBROOK AVE 91367

Certificate Information: 5921 N FALLBROOK AVE 91367

Application / Permit
22014-20000-01518
Plan Check / Job No.
B22VN04969
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 9'-0" X 27' PATIO. & 6'-5" X 26'-4" ADDITION TO EXTEND THE (E) LIVING ROOM, AND INTERIOR REMODEL TO THE (E) KITCHEN AND BATHROOM ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2022 APPLICANT
Assigned to Plan Check Engineer 4/4/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/27/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/7/2022 ALEC MOUSAKHANIAN
Applicant returned to address corrections 6/8/2022 ALEC MOUSAKHANIAN
Plan Check Approved 7/17/2022 LUIS RINCON
Building Plans Picked Up 7/26/2022 APPLICANT
Issued 7/27/2022 APPLICANT
CofO in Progress 11/1/2023 TROY SANDERS
Permit Finaled 1/15/2025 JOHN JANSON
CofO Issued 1/15/2025 JOHN JANSON
Permit Finaled 1/15/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/19/2022 CARLOS AGUILERA
Sewer availability Cleared 4/19/2022 CARLOS AGUILERA
ZA Case Cleared 4/19/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 4/20/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/21/2022 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 12/2/2022 Approved TROY SANDERS
Footing/Foundation/Slab 12/2/2022 Approved TROY SANDERS
Green Building Rough 12/2/2022 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 12/2/2022 Approved TROY SANDERS
Insulation 12/8/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/8/2022 Partial Approval JUSTIN HAWLEY
Shower Pan 12/8/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/27/2022 Partial Approval TROY SANDERS
Masonry Wall/Backfill 12/27/2022 Not Ready for Inspection TROY SANDERS
Shower Pan 12/27/2022 Approved TROY SANDERS
Drywall Nailing 12/30/2022 Not Ready for Inspection TROY SANDERS
Drywall Nailing 1/3/2023 Partial Approval MORRIS JACKSON
Drywall Nailing 1/6/2023 Approved JESUS PINEDA
Excavation/Setback/Form/Re-Bar 6/7/2023 Partial Approval HORACE FULTZ
Final 10/11/2023 Corrections Issued HORACE FULTZ
Green Building Final 10/11/2023 Not Ready for Inspection HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Not Ready HORACE FULTZ
Smoke Detectors 10/11/2023 Not Ready for Inspection HORACE FULTZ
Final 10/16/2023 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 10/16/2023 Approved TROY SANDERS
Final 10/31/2023 OK to Issue CofO TROY SANDERS
Green Building Final 10/31/2023 Approved TROY SANDERS