16611 W PARK LANE CIR 90049

Certificate Information: 16611 W PARK LANE CIR 90049

Application / Permit
22014-20000-01512
Plan Check / Job No.
B22VN04952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRST AND SECOND FLOOR ADDITION TO (E) 2-STORY SFD
Permit Issued
Issued on 9/23/2022
Issuing Office
Valley
Current Status
Issued on 9/23/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 MOHAMMAD ESMAILI
Corrections Issued 5/1/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/10/2022 OMID HEDAYAT
Building Plans Picked Up 5/11/2022 APPLICANT
Plan Check Approved 9/23/2022 MOHAMMAD ESMAILI
Issued 9/23/2022 APPLICANT

Permit Application Clearance Information

Distance to fire station Cleared 6/13/2022 RUEL COLE
Hydrant and Access approval Cleared 6/13/2022 RUEL COLE
Specific Plan Cleared 8/3/2022 OLGA AYALA
ZA Case Cleared 8/3/2022 OLGA AYALA
ZI Cleared 8/3/2022 OLGA AYALA
Roof/Waste drainage to street Cleared 9/7/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 9/8/2022 DINAH GARIN
Grading Pre-Inspection Cleared 9/23/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/13/2023 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 1/25/2023 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/25/2023 Partial Approval MICHAEL PELHAM
Rough-Elec/Plmb/HVAC 1/25/2023 Corrections Issued MICHAEL PELHAM
Drywall Nailing 2/3/2023 Partial Approval CHRISTOPHER WILSON
Insulation 2/3/2023 Partial Approval CHRISTOPHER WILSON
Shower Pan 2/3/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/10/2023 Partial Approval MICHAEL PELHAM
BUILDING-Rough-Frame 6/15/2023 Not Ready for Inspection CARLOS MATAMOROS
Final 6/15/2023 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 6/15/2023 Approved CARLOS MATAMOROS
Green Building Final 6/15/2023 Approved CARLOS MATAMOROS
Green Building Rough 6/15/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 6/15/2023 Approved CARLOS MATAMOROS