7859 N IRVINE AVE 91605

Certificate Information: 7859 N IRVINE AVE 91605

Application / Permit
22014-20000-01507
Plan Check / Job No.
B22VN04942
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-0" X 18'-9" & 22'-0" X 11'-7" FRONT AND REAR ADDITIONS TO THE (E) SFD PER WFPP FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 9/2/2022
Issuing Office
Metro
Current Status
Issued on 9/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/8/2022 ARTIN ZARUKIAN
Corrections Issued 4/11/2022 ARTIN ZARUKIAN
Building Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 8/12/2022 DANIEL ABRAMYAN
Plan Check Approved 8/17/2022 ADAM HEGAZI
Issued 9/2/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/29/2022 MEGAN GODINEZ
Sewer availability Cleared 4/29/2022 MEGAN GODINEZ
Low Impact Development Cleared 7/29/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/1/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 8/1/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 8/1/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 8/1/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/12/2022 Not Ready for Inspection DEANDRE HOFFMAN
ELECTRICAL-Rough 10/12/2022 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 10/12/2022 Corrections Issued DEANDRE HOFFMAN
Green Building Rough 10/12/2022 Not Ready for Inspection DEANDRE HOFFMAN
ELECTRICAL-Rough 10/18/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 10/25/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 10/25/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 10/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 10/25/2022 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 10/31/2022 Not Ready for Inspection WILLIAM WREN
Wood Frame 10/31/2022 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 11/2/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 11/9/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 11/9/2022 Approved CHRISTOPHER DELLEFIELD