17050 W EMPANADA PL 91436

Certificate Information: 17050 W EMPANADA PL 91436

Application / Permit
22014-20000-01502
Plan Check / Job No.
B22VN04927
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 5'-10 1/2" x 18'-4" COVERED ENTRYWAY TO HABITABLE SPACE AND 11' 3" X 29' 2" IRR.-SHAPE REAR ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING. NO NEW ROOF AREA.
Permit Issued
Issued on 12/22/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 GURUNATH NESARAJAH
Corrections Issued 4/8/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 9/15/2022 OMAR GARNICA
Applicant returned to address corrections 12/5/2022 ALEC MOUSAKHANIAN
Plan Check Approved 12/22/2022 HAYATO TSUCHIYA
Issued 12/22/2022 APPLICANT
CofO in Progress 12/26/2025 SEAN WIRCH
Permit Finaled 4/25/2026 MICHAEL PELHAM
CofO Issued 4/25/2026 MICHAEL PELHAM
Permit Finaled 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Construction near power lines Cleared 8/18/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/22/2022 LANNY MERRICK
ZA Case Cleared 11/15/2022 BRENNEN OBETO
Private street Cleared 12/6/2022 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/2/2024 Corrections Issued HENRY KIM
PLUMBING-Final 6/14/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/13/2024 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 8/20/2024 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 9/11/2024 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 11/14/2024 Approved ALEXANDER HANDY
HVAC-Rough 11/14/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 11/14/2024 Approved ALEXANDER HANDY
Wood Frame 11/14/2024 Approved ALEXANDER HANDY
Insulation 2/27/2025 Approved ALEXANDER HANDY
Drywall Nailing 3/14/2025 Approved JOHN KIDWELL
Shower Pan 3/14/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/23/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 10/29/2025 Approved JON MCHUGH
Final 10/29/2025 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 10/29/2025 Approved JON MCHUGH
Green Building Final 10/29/2025 Not Ready for Inspection JON MCHUGH
Green Building Rough 10/29/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved JON MCHUGH
Smoke Detectors 10/29/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 12/23/2025 Approved SEAN WIRCH
Final 12/23/2025 OK to Issue CofO SEAN WIRCH
Green Building Final 12/23/2025 Approved SEAN WIRCH
HVAC-Final 12/23/2025 Approved SEAN WIRCH
PLUMBING-Final 12/23/2025 Approved SEAN WIRCH
Smoke Detectors 12/23/2025 Approved SEAN WIRCH