13337 N GLADSTONE AVE 91342

Certificate Information: 13337 N GLADSTONE AVE 91342

Application / Permit
22014-20000-01499
Plan Check / Job No.
B22VN04926
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE. SCOPE WILL ALSO CONSIST OF AN ADDITION. ***BLDG SHALL BE SPRINKLERED PER NFPA 13D***
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 12/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/4/2022 MICHAEL LOPEZ
Corrections Issued 4/4/2022 MICHAEL LOPEZ
Applicant returned to address corrections 6/8/2022 MICHAEL LOPEZ
Applicant returned to address corrections 6/30/2022 MICHAEL LOPEZ
Plan Check Approved 7/13/2022 MICHAEL LOPEZ
Issued 7/14/2022 APPLICANT
CofO in Progress 12/22/2022 ARAM AVEDISIAN
CofO Issued 12/23/2022 MICHAEL SMITH
Permit Finaled 12/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/26/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 4/26/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/27/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/3/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 6/27/2022 KURT CORRAL

Contact Information

Contractor Better Together Builders Inc; Lic. No.: 1047689-B       ,
Engineer Dominguez,, Refugio; Lic. No.: NA50820       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/2/2022 Partial Approval ARAM AVEDISIAN
Pre-Inspection 8/18/2022 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 8/23/2022 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 8/26/2022 Partial Approval ARAM AVEDISIAN
Underground Mechanical 8/26/2022 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 8/30/2022 Approved ARAM AVEDISIAN
Deputy Drilled-In Anchors 9/13/2022 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 9/19/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 9/21/2022 Approved ASHLEY THOMPSON
HVAC-Rough 9/21/2022 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 9/21/2022 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 9/23/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 9/27/2022 Approved ARAM AVEDISIAN
HVAC-Rough 10/11/2022 Approved ARAM AVEDISIAN
Insulation 10/24/2022 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 10/24/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Sewer 10/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved MATTHEW NELSON
Insulation 10/31/2022 Approved MATTHEW NELSON
Special/Order Compliance 11/14/2022 Partial Inspection ARAM AVEDISIAN
Sewer 12/16/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/22/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/22/2022 Approved ARAM AVEDISIAN
Final 12/22/2022 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 12/22/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/22/2022 Approved ARAM AVEDISIAN
HVAC-Final 12/22/2022 Approved ARAM AVEDISIAN
MERV13>=Final 12/22/2022 Approved ARAM AVEDISIAN
MERV13>=Rough 12/22/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 12/22/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 12/22/2022 Approved ARAM AVEDISIAN