6104 N CARTWRIGHT AVE 91606
Certificate Information: 6104 N CARTWRIGHT AVE 91606
- Application / Permit
- 22014-20000-01498
- Plan Check / Job No.
- B22VN04922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Bedroom addition to (E) SFD
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2022 | HERNAN ARREOLA |
| Corrections Issued | 4/18/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/3/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/30/2022 | HERNAN ARREOLA |
| Plan Check Approved | 7/6/2022 | HERNAN ARREOLA |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 11/7/2023 | JOHN HAYES |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 4/21/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/21/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Mr Build Home Improvement Company; Lic. No.: 439166-B | , |
| Contractor | Mr Build Solar Electric; Lic. No.: 439166-B | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 8/11/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/30/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 10/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | JOHN HAYES |
| Green Building Rough | 10/31/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/31/2022 | Approved | JOHN HAYES |
| Insulation | 11/28/2022 | Corrections Issued | JORDAN KUTZLY |
| Interior/Exterior Lathing | 11/28/2022 | Conditional Approval | JORDAN KUTZLY |
| Shower Pan | 11/28/2022 | Approved | JORDAN KUTZLY |
| Insulation | 12/9/2022 | Approved | JORDAN KUTZLY |
| Interior/Exterior Lathing | 12/9/2022 | Approved | JORDAN KUTZLY |
| Drywall Nailing | 12/19/2022 | Approved | JOHN COLEMAN |
| Final | 11/6/2023 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 11/6/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 11/6/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 11/29/2023 | Corrections Issued | JOHN HAYES |