7536 N NESTLE AVE 91335

Certificate Information: 7536 N NESTLE AVE 91335

Application / Permit
22014-20000-01495
Plan Check / Job No.
B22VN04913
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 20'X20' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 20'X13'4" STORAGE & BEDROOM ADDITIONN - ALL WORK PER ENGINEER.
Permit Issued
Issued on 8/19/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/8/2022 HAYATO TSUCHIYA
Corrections Issued 4/12/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 7/9/2022 HAYATO TSUCHIYA
Building Plans Picked Up 7/12/2022 APPLICANT
Plan Check Approved 8/19/2022 DANIEL ABRAMYAN
Issued 8/19/2022 APPLICANT
CofO in Progress 11/22/2023 JEFFREY BULL
Permit Finaled 7/23/2024 JOHN JANSON
CofO Issued 7/23/2024 JOHN JANSON
Permit Finaled 7/23/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/19/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CARLOS AGUILERA
Sewer availability Cleared 4/21/2022 CARLOS AGUILERA
Construction near power lines Cleared 6/27/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/2/2023 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 6/6/2023 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 6/12/2023 Approved JEFFREY BULL
Insulation 6/26/2023 Approved JEFFREY BULL
Drywall Nailing 6/27/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 6/27/2023 Not Ready for Inspection JEFFREY BULL
Drywall Nailing 6/30/2023 Approved JUSTIN HAWLEY
Green Building Rough 6/30/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/30/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 7/10/2023 Corrections Issued SEAN WIRCH
Final 7/10/2023 Corrections Issued SEAN WIRCH
Green Building Final 7/10/2023 Not Ready for Inspection SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/10/2023 SGSOV Not Ready SEAN WIRCH
Smoke Detectors 7/10/2023 Not Ready for Inspection SEAN WIRCH
Green Building Final 9/14/2023 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 11/13/2023 Approved JEFFREY BULL
Final 11/13/2023 Not Ready for Inspection JEFFREY BULL
Green Building Final 11/13/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 11/13/2023 Approved JEFFREY BULL
Final 11/22/2023 OK to Issue CofO JEFFREY BULL