3866 S EDGEHILL DR 90008

Certificate Information: 3866 S EDGEHILL DR 90008

Application / Permit
22014-20000-01481
Plan Check / Job No.
B22VN04860
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
10'-9" X 1'-6" ADDITION TO ENLARGE AND REMODEL KITCHEN AND LAUNDRY ROOM. 14'-6" X 6'-7" ADDITION TO RELOCATE MASTER BATHROOM AND CLOSET.
Permit Issued
Issued on 8/5/2022
Issuing Office
Metro
Current Status
Issued on 8/5/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 JEROME MAGAT PALMA
Corrections Issued 4/7/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 5/17/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 6/7/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 7/7/2022 JEROME MAGAT PALMA
Plan Check Approved 7/25/2022 JEROME MAGAT PALMA
Building Plans Picked Up 7/29/2022 APPLICANT
Issued 8/5/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/10/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 5/23/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2022 Partial Inspection ANTHONY EGSON
Footing/Foundation/Slab 9/28/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 11/16/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 11/16/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 12/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/30/2022 Approved ANTHONY EGSON
Deputy Wood Construction 1/9/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/11/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 1/11/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 1/11/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/11/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 1/11/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/19/2023 Approved ANTHONY EGSON
Green Building Rough 1/19/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/19/2023 Approved ANTHONY EGSON
Insulation 1/25/2023 Partial Approval ANTHONY EGSON
Drywall Nailing 1/31/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 2/7/2023 Not Ready for Inspection STUART CHAPMAN
Shower Pan 2/15/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 3/3/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 8/15/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 8/15/2023 Approved ANTHONY EGSON
PLUMBING-Final 8/15/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 8/16/2023 Not Ready for Inspection ANTHONY EGSON