6451 N BLEWETT AVE 91406
Certificate Information: 6451 N BLEWETT AVE 91406
- Application / Permit
- 22014-20000-01472
- Plan Check / Job No.
- B22VN04838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH AN ADDITION TO A DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 5/15/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2022 | CARLOS MONTES |
| Corrections Issued | 4/21/2022 | CARLOS MONTES |
| Plan Check Approved | 5/11/2022 | CARLOS MONTES |
| Issued | 5/15/2022 | APPLICANT |
| CofO in Progress | 12/12/2022 | RAUL OLAGI |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/2/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 5/11/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2022 | No Access for Inspection | ALAN MORELOS |
| Deputy Drilled-In Anchors | 6/24/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/1/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 7/1/2022 | Corrections Issued | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/10/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/10/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 8/10/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/10/2022 | Approved | RAUL OLAGI |
| Sewer | 8/10/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 8/10/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/23/2022 | No Access for Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | ALAN MORELOS |
| HVAC-Rough | 8/23/2022 | Corrections Issued | ALAN MORELOS |
| Wood Frame | 8/23/2022 | Not Ready for Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 8/30/2022 | No Access for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/2/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 9/2/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 9/2/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 9/2/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/2/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/7/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 9/7/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/12/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 9/19/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/19/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Rough | 10/11/2022 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 10/11/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 10/26/2022 | Corrections Issued | RAUL OLAGI |
| Final | 10/26/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 10/26/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 10/26/2022 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 10/26/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 11/15/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 11/15/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 11/15/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 11/15/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/12/2022 | Approved | RAUL OLAGI |
| Final | 12/12/2022 | OK to Issue CofO | RAUL OLAGI |