5521 N SIMPSON AVE 91607

Certificate Information: 5521 N SIMPSON AVE 91607

Application / Permit
22014-20000-01470
Plan Check / Job No.
B22VN04836
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO DETACHED ADU PER ORDINANCE. INCLUDES ADDITION.
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/5/2022 CARLOS MONTES
Corrections Issued 4/6/2022 CARLOS MONTES
Plan Check Approved 4/22/2022 CARLOS MONTES
Issued 4/27/2022 APPLICANT
CofO in Progress 10/13/2023 RYAN SALAZAR
Permit Finaled 5/15/2024 RUBEN SALAS
CofO Issued 5/15/2024 RUBEN SALAS
Permit Finaled 5/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/12/2022 CHRIS CHAHBAZ
Roof/Waste drainage to street Cleared 4/12/2022 CHRIS CHAHBAZ
Specific Plan Cleared 4/12/2022 ERIN NASH
Eng Process Fee Ord 176,300 Cleared 4/15/2022 CHRIS CHAHBAZ
Sewer availability Cleared 4/15/2022 CHRIS CHAHBAZ

Contact Information

Contractor Platinum Home Remodeling Inc ; Lic. No.: 1060535-B       ,
Contractor Platinum Home Remodeling Inc; Lic. No.: 1060535-B       ,
Engineer Hsiao,, Stephanie; Lic. No.: C75937 255 N MICHIGAN AVE #5      PASADENA, CA 91106

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/17/2022 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 6/21/2022 Approved THOMAS FINNILA
Footing/Foundation/Slab 6/21/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 7/11/2022 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/11/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Green Building Rough 7/11/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Rough 7/11/2022 Approved CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 7/11/2022 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 7/13/2022 Corrections Issued THOMAS FINNILA
HVAC-Rough 7/18/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/27/2022 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 7/27/2022 Corrections Issued CALEB MEISTER
Insulation 7/27/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 8/1/2022 Conditional Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 8/1/2022 Approved THOMAS FINNILA
Drywall Nailing 8/8/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/16/2022 Partial Approval THOMAS FINNILA
Shower Pan 8/16/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/29/2023 Approved JACK KARGODORIAN
Final 9/29/2023 Corrections Issued JACK KARGODORIAN
Green Building Final 9/29/2023 Approved JACK KARGODORIAN
Green Building Rough 9/29/2023 Approved JACK KARGODORIAN
MERV13>=Final 9/29/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 9/29/2023 Approved JACK KARGODORIAN
Final 10/6/2023 Partial Approval RYAN SALAZAR
Final 10/13/2023 OK to Issue CofO RYAN SALAZAR