5337 N BUFFALO AVE 91401
Certificate Information: 5337 N BUFFALO AVE 91401
- Application / Permit
- 22014-20000-01466
- Plan Check / Job No.
- B22VN04809
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 21'- 6" X 13' ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/25/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 5/24/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/25/2022 | ALEC MOUSAKHANIAN |
| Issued | 5/25/2022 | APPLICANT |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| CofO in Progress | 2/2/2024 | MISAEL ESPARZA |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/19/2022 | CARLOS AGUILERA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Value Up Renovation & Construction; Lic. No.: 1031128-B | 6542 BELLAIRE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/18/2023 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/18/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/25/2023 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 10/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 10/25/2023 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 10/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 10/25/2023 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 10/27/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 11/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/7/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 11/13/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/16/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 11/16/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 11/16/2023 | Approved | MISAEL ESPARZA |
| Insulation | 11/22/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/22/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 11/22/2023 | Partial Inspection | MISAEL ESPARZA |
| Drywall Nailing | 11/27/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/27/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/27/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/29/2024 | Approved | MISAEL ESPARZA |
| Final | 1/29/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/29/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/29/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 1/29/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 1/29/2024 | Approved | MISAEL ESPARZA |
| Final | 2/1/2024 | OK to Issue CofO | MISAEL ESPARZA |