8418 N FULLBRIGHT AVE 91306

Certificate Information: 8418 N FULLBRIGHT AVE 91306

Application / Permit
22014-20000-01461
Plan Check / Job No.
B22VN04774
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH A PORCH ADDITION
Permit Issued
Issued on 8/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/1/2022 SERGIO MUNIZ
Corrections Issued 4/3/2022 SERGIO MUNIZ
Building Plans Picked Up 4/7/2022 APPLICANT
Applicant returned to address corrections 2/1/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 5/31/2023 ISIS ARGUETA
Plan Check Approved 8/17/2023 JESSE ARELLANO
Issued 8/21/2023 APPLICANT
CofO in Progress 8/13/2025 JEFFREY HARTLINE
Permit Finaled 9/19/2025 JOHN JANSON
CofO Issued 9/19/2025 JOHN JANSON
Permit Finaled 9/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/2/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 7/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/2/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/5/2022 CARLOS AGUILERA
Construction near power lines Cleared 5/31/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval JEFFREY HARTLINE
Shower Pan 7/8/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 7/15/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 7/15/2024 Approved JEFFREY HARTLINE
Green Building Rough 7/15/2024 Approved JEFFREY HARTLINE
HVAC-Rough 7/15/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 7/15/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 7/15/2024 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 7/15/2024 Approved JEFFREY HARTLINE
Insulation 7/22/2024 Approved HENRY KIM
Drywall Nailing 7/26/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 7/26/2024 Partial Approval JEFFREY HARTLINE
Final 8/12/2025 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 8/12/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 8/12/2025 Approved JEFFREY HARTLINE
Service/Power Release 8/25/2025 Approved JEFFREY HARTLINE