2450 W 60TH ST 90043

Certificate Information: 2450 W 60TH ST 90043

Application / Permit
22014-20000-01453
Plan Check / Job No.
B22VN04738
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
28' x 24' IRR ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) 18' X 16' ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 12/19/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/1/2022 SERGIO MUNIZ
Corrections Issued 4/2/2022 SERGIO MUNIZ
Building Plans Picked Up 4/7/2022 APPLICANT
Plan Check Approved 12/9/2022 ISIS ARGUETA
Issued 12/19/2022 APPLICANT
CofO in Progress 2/1/2024 ENRIQUE MIRELES
Permit Finaled 2/7/2024 DEROLD HAUFF
CofO Issued 2/7/2024 DEROLD HAUFF
Permit Finaled 2/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/13/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 4/13/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 5/18/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 5/18/2022 CHRISTOPHER ROCHA
Construction near power lines Cleared 11/21/2022 RIDWAN HARDY
Hold Cleared 4/4/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/25/2023 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 1/30/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 2/2/2023 Approved ENRIQUE MIRELES
Underground Mechanical 4/11/2023 Approved ENRIQUE MIRELES
Wood Frame 4/11/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 4/14/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/14/2023 Approved ENRIQUE MIRELES
Underground Mechanical 4/14/2023 Approved ENRIQUE MIRELES
Wood Frame 4/14/2023 Approved ENRIQUE MIRELES
Insulation 4/27/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/27/2023 Corrections Issued ENRIQUE MIRELES
Drywall Nailing 5/3/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 5/3/2023 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 7/28/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 9/15/2023 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 10/30/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/7/2023 Approved ENRIQUE MIRELES
Final 12/7/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 12/7/2023 Approved ENRIQUE MIRELES
Green Building Final 12/7/2023 Approved ENRIQUE MIRELES
Green Building Rough 12/7/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/7/2023 Approved ENRIQUE MIRELES
Final 12/21/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 12/21/2023 Approved ENRIQUE MIRELES