5021-5023 S CIMARRON ST 90062
Certificate Information: 5021-5023 S CIMARRON ST 90062
- Application / Permit
- 22014-20000-01439
- Plan Check / Job No.
- B22VN04706
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-0" X 31'-0" ADDITION TO THE (E) SFD AND 31'-0" X 26'-0" IRREGULAR SHAPED ADDITION OF ACCESSORY DWELLING UNIT TO THE (E) SFD PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 4/4/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 5/24/2022 | ARTIN ZARUKIAN |
| Issued | 5/25/2022 | APPLICANT |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| CofO in Progress | 1/9/2023 | SABAS ALONSO |
| CofO Issued | 1/11/2023 | DEROLD HAUFF |
| Permit Finaled | 1/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 5/16/2022 | ANTHONY VARGAS |
| Sewer availability | Cleared | 5/16/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/13/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/13/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/13/2022 | Approved | SABAS ALONSO |
| Wood Frame | 7/28/2022 | Partial Approval | SABAS ALONSO |
| Insulation | 8/2/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/4/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 10/4/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 10/4/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/14/2022 | Corrections Issued | STUART CHAPMAN |
| Insulation | 10/18/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/21/2022 | Approved | SABAS ALONSO |
| Shower Pan | 10/31/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | SABAS ALONSO |
| Final | 12/2/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/2/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/2/2022 | Approved | SABAS ALONSO |
| Final | 12/9/2022 | Partial Approval | SABAS ALONSO |
| Green Building Final | 12/9/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 1/6/2023 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 1/6/2023 | Approved | SABAS ALONSO |