5021-5023 S CIMARRON ST 90062

Certificate Information: 5021-5023 S CIMARRON ST 90062

Application / Permit
22014-20000-01439
Plan Check / Job No.
B22VN04706
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-0" X 31'-0" ADDITION TO THE (E) SFD AND 31'-0" X 26'-0" IRREGULAR SHAPED ADDITION OF ACCESSORY DWELLING UNIT TO THE (E) SFD PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 5/25/2022
Issuing Office
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 ARTIN ZARUKIAN
Corrections Issued 4/4/2022 ARTIN ZARUKIAN
Plan Check Approved 5/24/2022 ARTIN ZARUKIAN
Issued 5/25/2022 APPLICANT
Building Plans Picked Up 6/1/2022 APPLICANT
CofO in Progress 1/9/2023 SABAS ALONSO
CofO Issued 1/11/2023 DEROLD HAUFF
Permit Finaled 1/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/14/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/16/2022 AMAAN MALIK
Low Impact Development Cleared 5/16/2022 ANTHONY VARGAS
Sewer availability Cleared 5/16/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 5/18/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/13/2022 Approved SABAS ALONSO
Underground Mechanical 6/13/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/13/2022 Approved SABAS ALONSO
Wood Frame 7/28/2022 Partial Approval SABAS ALONSO
Insulation 8/2/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 10/4/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 10/4/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 10/4/2022 Partial Approval SABAS ALONSO
Rough-Elec/Plmb/HVAC 10/4/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/14/2022 Corrections Issued STUART CHAPMAN
Insulation 10/18/2022 Approved SABAS ALONSO
Drywall Nailing 10/21/2022 Approved SABAS ALONSO
Shower Pan 10/31/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/2/2022 Approved SABAS ALONSO
Final 12/2/2022 Corrections Issued SABAS ALONSO
Green Building Final 12/2/2022 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/2/2022 Approved SABAS ALONSO
Final 12/9/2022 Partial Approval SABAS ALONSO
Green Building Final 12/9/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Approved SABAS ALONSO
Final 1/6/2023 OK to Issue CofO SABAS ALONSO
Service/Power Release 1/6/2023 Approved SABAS ALONSO