635 1/2 W 43RD ST 90037
Certificate Information: 635 1/2 W 43RD ST 90037
- Application / Permit
- 22014-20000-01434
- Plan Check / Job No.
- B22VN04690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing detached garage into an ADU with a 1 story addition per ordinance.
- Permit Issued
- Issued on 11/4/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/31/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 9/6/2022 | MICHAEL LOPEZ |
| Issued | 11/4/2022 | APPLICANT |
| CofO in Progress | 3/21/2024 | SABAS ALONSO |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 4/11/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/5/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 1/26/2023 | Partial Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/11/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/23/2023 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 5/23/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/30/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/30/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/12/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 7/12/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 7/12/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 7/18/2023 | Approved | CHARLES BOGHOSKHAN |
| HVAC-Rough | 7/18/2023 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/18/2023 | Approved | CHARLES BOGHOSKHAN |
| Underground Mechanical | 7/18/2023 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 8/10/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/16/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/21/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 8/23/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | SABAS ALONSO |
| Final | 2/9/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/9/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 2/9/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 2/9/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 2/9/2024 | Approved | SABAS ALONSO |
| Final | 2/22/2024 | No Access for Inspection | SABAS ALONSO |
| Final | 2/27/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 3/7/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 3/13/2024 | OK to Issue CofO | SABAS ALONSO |