19112 W FRIAR ST 91335

Certificate Information: 19112 W FRIAR ST 91335

Application / Permit
22014-20000-01423
Plan Check / Job No.
B22VN04657
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION AND MAJOR REMODEL TO (E) ONE STORY SFD_ REMOVE AND REPLACE (E) ROOF CONFIG. CONVERT (E) GARAGE TO LIVING ROOM. EXTEND MASTER BEDROOM. ADD 2-CAR GARAGE, MUD ROOM, LAUNDRY ROOM, AND ROOFTOP DECK_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 7/19/2023
Issuing Office
Valley
Current Status
Issued on 7/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 DAWN MC NULTY
Corrections Issued 5/31/2022 DAWN MC NULTY
Quality Review Completed 6/2/2022 STEVEN KIM
Building Plans Picked Up 6/10/2022 APPLICANT
Applicant returned to address corrections 6/20/2023 DAWN MC NULTY
Plan Check Approved 7/19/2023 DAWN MC NULTY
Issued 7/19/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/28/2022 CARLOS AGUILERA
Permit Cleared 11/28/2022 CARLOS AGUILERA
Sewer availability Cleared 11/28/2022 CARLOS AGUILERA
CPC Cleared 11/30/2022 DANG NGUYEN
Low Impact Development Cleared 6/30/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/5/2023 NIKKI ZULUETA
ZI Cleared 7/5/2023 JASON CHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mah,, Edwin Poy-Dor; Lic. No.: C27141 1740 APPIAN WAY      MONTEBELLO, CA 90640

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2023 Partial Inspection JOHN KIDWELL
Deputy Drilled-In Anchors 9/25/2023 Conditional Approval JON MCHUGH
BUILDING-Rough-Frame 10/16/2023 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 10/16/2023 Corrections Issued JON MCHUGH
Deputy Steel/Welding 10/19/2023 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 11/1/2023 Corrections Issued JON MCHUGH
Pre-Inspection 3/4/2024 Partial Approval JON MCHUGH
Deputy Other (see comments) 3/26/2024 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 4/3/2024 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Corrections Issued JON MCHUGH
PLUMBING-Rough 4/26/2024 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval JON MCHUGH
Deputy Steel/Welding 6/14/2024 Conditional Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 12/26/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 12/26/2024 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 12/26/2024 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 1/15/2025 Partial Approval JON MCHUGH
HVAC-Rough 2/7/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 2/7/2025 Corrections Issued JON MCHUGH
Shower Pan 2/7/2025 Approved JON MCHUGH
ELECTRICAL-Rough 3/12/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 3/12/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 3/18/2025 Partial Approval JON MCHUGH
ELECTRICAL-Rough 3/18/2025 Approved JON MCHUGH
HVAC-Rough 3/18/2025 Approved JON MCHUGH
Verify Sprinkler Sign Off 3/18/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 3/25/2025 Approved JON MCHUGH
Green Building Rough 3/25/2025 Approved JON MCHUGH
Insulation 3/25/2025 Corrections Issued JON MCHUGH
Drywall Nailing 4/7/2025 Approved JON MCHUGH
Interior/Exterior Lathing 4/7/2025 Approved JON MCHUGH
Final 5/29/2025 Not Ready for Inspection JON MCHUGH
Green Building Final 5/29/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 5/29/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 6/3/2025 Corrections Issued JON MCHUGH
Service/Power Release 6/3/2025 Approved JON MCHUGH
Final 10/21/2025 Corrections Issued JON MCHUGH
Green Building Final 10/21/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Required JON MCHUGH
Smoke Detectors 10/21/2025 Not Ready for Inspection JON MCHUGH