9411 N WEXFORD DR 91042
Certificate Information: 9411 N WEXFORD DR 91042
- Application / Permit
- 22014-20000-01415
- Plan Check / Job No.
- B22VN04626
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING PER ENGINEER.
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Current Status
- CofO Issued on 9/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | SERGIO MUNIZ |
| Corrections Issued | 4/2/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| Plan Check Approved | 11/28/2023 | PINANK PATEL |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 8/29/2024 | DAVID ANDERSON |
| Permit Finaled | 9/23/2024 | DANIEL ORRANTE |
| CofO Issued | 9/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/15/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 4/20/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 10/26/2023 | RYAN LY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Corrections Issued | DAVID ANDERSON |
| Gas Test | 1/31/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 2/2/2024 | Approved | DAVID ANDERSON |
| Gas Test | 2/2/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 2/2/2024 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/22/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 2/22/2024 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 2/23/2024 | Conditional Approval | DAVID MATSON |
| Drywall Nailing | 2/29/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Approved | DAVID ANDERSON |
| Insulation | 2/29/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/29/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | MATTHEW NELSON |
| Final | 7/16/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/16/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 7/16/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 7/16/2024 | Approved | MATTHEW NELSON |
| Final | 8/28/2024 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 8/28/2024 | Approved | DAVID ANDERSON |