16003-16005 W TUPPER ST 91343
Certificate Information: 16003-16005 W TUPPER ST 91343
- Application / Permit
- 22014-20000-01407
- Plan Check / Job No.
- B22VN04602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 5' X 11' ADDITION TO (E) SFD FOR A NEW BATHROOM TO THE (E) SFD, ALL WORK PER WFPP
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2022 | RARES BODEA |
| Corrections Issued | 3/30/2022 | RARES BODEA |
| Plan Check Approved | 4/29/2022 | MOHAMMAD ESMAILI |
| Issued | 4/29/2022 | APPLICANT |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| CofO in Progress | 11/6/2023 | RAUL OLAGI |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
| CofO Issued | 12/27/2023 | RUBEN SALAS |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/19/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 4/21/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/15/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/31/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/30/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 6/30/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 6/30/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/30/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/30/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | RAUL OLAGI |
| Shower Pan | 7/10/2023 | Not Ready for Inspection | RAUL OLAGI |
| Drywall Nailing | 8/17/2023 | Approved | RAUL OLAGI |
| Insulation | 8/17/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/17/2023 | Approved | RAUL OLAGI |
| Shower Pan | 8/17/2023 | Approved | RAUL OLAGI |
| Final | 9/27/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/27/2023 | Approved | RAUL OLAGI |
| Smoke Detectors | 9/27/2023 | Approved | RAUL OLAGI |
| Final | 11/6/2023 | OK to Issue CofO | RAUL OLAGI |