1626 N WINONA BLVD 90027
Certificate Information: 1626 N WINONA BLVD 90027
- Application / Permit
- 22014-20000-01397
- Plan Check / Job No.
- B22VN04568
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (6'-1"x33'-5"), 429 SQFT GROUND/2ND FLOOR ADDITION AND MINOR ALTERATION TO (E) SFD INCLUDING NEW BATH AND BEDROOM
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | PETER MOSESIAN |
| Corrections Issued | 4/10/2022 | PETER MOSESIAN |
| Quality Review Completed | 4/15/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Plan Check Approved | 9/1/2022 | PETER MOSESIAN |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 10/23/2024 | BRIAN SULLIVAN |
| No Progress | 11/24/2024 | DEROLD HAUFF |
| CofO in Progress | 11/24/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
| CofO Issued | 12/7/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/18/2022 | JEANETTE VONG |
| Specific Plan | Cleared | 6/7/2022 | VALENTINA KNOX |
| ZI | Cleared | 6/7/2022 | VALENTINA KNOX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/12/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/20/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Pre-Inspection | 12/23/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 1/4/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/13/2023 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/13/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 3/13/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 3/13/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/13/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/17/2023 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 3/17/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/17/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/24/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/17/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/24/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 6/2/2023 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/7/2023 | No Access for Inspection | STUART CHAPMAN |
| Drywall Nailing | 10/5/2023 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 10/10/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Shower Pan | 10/12/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/30/2023 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/21/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/21/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/21/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/21/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | SCOTT FINNILA |
| Final | 7/1/2024 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 7/1/2024 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 7/1/2024 | Approved | SCOTT FINNILA |
| Final | 10/7/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/18/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/22/2024 | OK to Issue CofO | BRIAN SULLIVAN |