1626 N WINONA BLVD 90027

Certificate Information: 1626 N WINONA BLVD 90027

Application / Permit
22014-20000-01397
Plan Check / Job No.
B22VN04568
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(6'-1"x33'-5"), 429 SQFT GROUND/2ND FLOOR ADDITION AND MINOR ALTERATION TO (E) SFD INCLUDING NEW BATH AND BEDROOM
Permit Issued
Issued on 9/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 PETER MOSESIAN
Corrections Issued 4/10/2022 PETER MOSESIAN
Quality Review Completed 4/15/2022 OMID HEDAYAT
Building Plans Picked Up 4/18/2022 APPLICANT
Plan Check Approved 9/1/2022 PETER MOSESIAN
Issued 9/12/2022 APPLICANT
CofO in Progress 10/23/2024 BRIAN SULLIVAN
No Progress 11/24/2024 DEROLD HAUFF
CofO in Progress 11/24/2024 DEROLD HAUFF
Permit Finaled 12/7/2024 DEROLD HAUFF
CofO Issued 12/7/2024 DEROLD HAUFF
Permit Finaled 12/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 4/18/2022 JEANETTE VONG
Sewer availability Cleared 4/18/2022 JEANETTE VONG
Specific Plan Cleared 6/7/2022 VALENTINA KNOX
ZI Cleared 6/7/2022 VALENTINA KNOX

Contact Information

Contractor Owner-Builder       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/12/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/17/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/20/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/2/2022 Partial Approval JOAQUIN GREENOUGH
Pre-Inspection 12/23/2022 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 1/4/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/13/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 3/13/2023 Approved BRIAN SULLIVAN
Green Building Rough 3/13/2023 Approved BRIAN SULLIVAN
HVAC-Rough 3/13/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/13/2023 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 3/17/2023 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 3/17/2023 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/17/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 3/24/2023 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/17/2023 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/24/2023 Partial Approval JOAQUIN GREENOUGH
Insulation 6/2/2023 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/7/2023 No Access for Inspection STUART CHAPMAN
Drywall Nailing 10/5/2023 Approved JOAQUIN GREENOUGH
Shower Pan 10/10/2023 Corrections Issued JOAQUIN GREENOUGH
Shower Pan 10/12/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/30/2023 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/21/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 6/21/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 6/21/2024 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 6/21/2024 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/1/2024 Approved SCOTT FINNILA
Final 7/1/2024 Corrections Issued SCOTT FINNILA
Green Building Final 7/1/2024 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved SCOTT FINNILA
Smoke Detectors 7/1/2024 Approved SCOTT FINNILA
Final 10/7/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 10/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 10/18/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 10/22/2024 OK to Issue CofO BRIAN SULLIVAN