18237 W WEDDINGTON ST 91356

Certificate Information: 18237 W WEDDINGTON ST 91356

Application / Permit
22014-20000-01384
Plan Check / Job No.
B22VN04508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY GROUND FLOOR ADDITION AND INTERIOR STRUCTURAL REMODEL TO (E) 1-STORY SFD W/ (E) ATT. 2-CAR GARAGE.
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
Issued on 5/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 MAHNAZ NOURHASHEMI
Corrections Issued 4/28/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 5/5/2022 SAI KHUM
Building Plans Picked Up 5/10/2022 APPLICANT
Plan Check Approved 3/30/2023 CARLOS MONTES
Issued 5/19/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/23/2022 DAGOVERTO GUERRERO
Watercourse Cleared 11/28/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 3/1/2023 LUIS LUVANO
Sewer availability Cleared 3/3/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 3/4/2023 DAGOVERTO GUERRERO

Contact Information

Architect , ; Lic. No.: C33595       ,
Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/18/2023 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/24/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 7/24/2023 Approved SEAN HAUPT
PLUMBING-Rough 8/11/2023 Partial Approval ALEXANDER HANDY
Sewer 8/11/2023 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Conditional Approval JOHN KIDWELL
Special/Order Compliance 8/15/2023 Partial Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Approved SEAN HAUPT
Deputy Wood Construction 9/22/2023 Approved SEAN WIRCH
ELECTRICAL-Rough 10/19/2023 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Approved SEAN HAUPT
ELECTRICAL-Rough 11/20/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 11/20/2023 Approved SEAN HAUPT
PLUMBING-Rough 11/20/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/7/2023 Approved SEAN HAUPT
Green Building Rough 12/7/2023 Approved SEAN HAUPT
HVAC-Rough 12/7/2023 Approved SEAN HAUPT
MERV13>=Rough 12/7/2023 Approved SEAN HAUPT
Drywall Nailing 1/10/2024 Approved SEAN HAUPT
Insulation 1/10/2024 Approved SEAN HAUPT
Shower Pan 1/10/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 1/31/2024 Approved SEAN HAUPT
ELECTRICAL-Final 7/5/2024 Approved JOHN KIDWELL
HVAC-Final 7/5/2024 Approved JOHN KIDWELL
PLUMBING-Final 7/5/2024 Approved JOHN KIDWELL
Service/Power Release 7/5/2024 Approved JOHN KIDWELL
Pre-Inspection 8/23/2024 Partial Inspection JOHN KIDWELL
Final 5/6/2026 Not Ready for Inspection JOHN KIDWELL
Green Building Final 5/6/2026 Approved JOHN KIDWELL
MERV13>=Final 5/6/2026 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved JOHN KIDWELL
Smoke Detectors 5/6/2026 Approved JOHN KIDWELL