7454-7456 N MAMMOTH AVE 91405
Certificate Information: 7454-7456 N MAMMOTH AVE 91405
- Application / Permit
- 22014-20000-01376
- Plan Check / Job No.
- B22VN04492
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* ATTACHED ADU (49'-6" X 23'-5") ADDITION (ZC 819 SF) TO (E) SFD WITH (E) ATTACHED GARAGE PER LAMC 12.22A.33(c) AND (e). **The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | VIVIAN LAO |
| Corrections Issued | 4/1/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 4/28/2022 | VIVIAN LAO |
| Plan Check Approved | 5/3/2022 | VIVIAN LAO |
| Issued | 5/3/2022 | APPLICANT |
| CofO in Progress | 9/19/2023 | GREGG CUMMINGS |
| Permit Finaled | 10/15/2023 | RUBEN SALAS |
| CofO Issued | 10/15/2023 | RUBEN SALAS |
| Permit Finaled | 10/15/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 4/12/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/24/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 10/24/2022 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 10/25/2022 | Conditional Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/3/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/17/2023 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/25/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/25/2023 | Approved | GREGG CUMMINGS |
| Wood Frame | 1/25/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 2/9/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 2/9/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/14/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 2/14/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 2/14/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/17/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/17/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/17/2023 | Approved | GREGG CUMMINGS |
| Insulation | 2/23/2023 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 2/27/2023 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 3/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/9/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 7/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 7/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/6/2023 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 7/6/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 7/6/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | DAVID MATSON |
| Final | 7/19/2023 | Corrections Issued | DAVID MATSON |
| Green Building Final | 7/19/2023 | Approved | DAVID MATSON |
| Final | 9/7/2023 | Corrections Issued | THOMAS FINNILA |
| Final | 9/18/2023 | OK to Issue CofO | GREGG CUMMINGS |