1840 N SAN YSIDRO DR 90210
Certificate Information: 1840 N SAN YSIDRO DR 90210
- Application / Permit
- 22014-20000-01372
- Plan Check / Job No.
- B22VN04488
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO MOST OF (E) INT. AND EXT. WALLS AND ERECT AN IRR. SHAPED 57'-9" x 70'-9 1/4" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS AT REAR; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | SEAN SHAHMIRI |
| Corrections Issued | 4/18/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 4/22/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Applicant returned to address corrections | 12/15/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 12/21/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 1/23/2023 | SEAN SHAHMIRI |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 7/23/2025 | SEAN HAUPT |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
| CofO Issued | 7/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/11/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 8/15/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2022 | JENSON LEE |
| Construction within easement | Cleared | 11/15/2022 | OSCAR CASTRO |
| Hydrant and Access approval | Cleared | 12/15/2022 | JOHN CONNEALLY |
| Miscellaneous | Cleared | 12/21/2022 | SAUL GARCIA |
| Low Impact Development | Cleared | 1/19/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/20/2023 | JEANIE LAM |
Contact Information
| Architect | Osuch,, Edward M; Lic. No.: C32544 | 6191 ST ALBANS STREET # A LOS ANGELES, CA 90042 |
| Contractor | Trochez Construction Inc; Lic. No.: 1097458-B | 227 E 43RD STREET LOS ANGELES, CA 90011 |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 1176 N KNOLLWOOD CT ANAHEIM, CA 92801 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 3/22/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 3/24/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/28/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 4/5/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 5/11/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/25/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 8/29/2023 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 8/29/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 8/29/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 9/6/2023 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 9/6/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/19/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 9/19/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 9/19/2023 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 9/26/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 9/26/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | BRENDAN LOONEY |
| Green Building Rough | 10/2/2023 | Approved | BRENDAN LOONEY |
| Insulation | 10/6/2023 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 10/11/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 10/13/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 10/13/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/3/2023 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 11/3/2023 | Corrections Issued | BRENDAN LOONEY |
| Sewer | 1/17/2024 | Partial Approval | BRENDAN LOONEY |
| Special/Order Compliance | 1/24/2024 | Order to Comply Issued | BRENDAN LOONEY |
| Sewer | 1/29/2024 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 6/21/2024 | Approved | SEAN HAUPT |
| Service/Power Release | 6/21/2024 | Approved | SEAN HAUPT |
| Final | 6/12/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 6/12/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 6/12/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 6/17/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 6/17/2025 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 7/2/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Final | 7/2/2025 | Partial Approval | SEAN HAUPT |
| Final | 7/9/2025 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 7/9/2025 | Approved | SEAN HAUPT |
| HVAC-Final | 7/9/2025 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Final | 7/9/2025 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 7/9/2025 | Not Ready for Inspection | SEAN HAUPT |
| Final | 7/21/2025 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 7/21/2025 | Approved | SEAN HAUPT |
| Final | 7/22/2025 | OK to Issue CofO | SEAN HAUPT |