22650 W CASS AVE 91364
Certificate Information: 22650 W CASS AVE 91364
- Application / Permit
- 22014-20000-01370
- Plan Check / Job No.
- B22VN04483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO FIRST FLOOR TO THE (E) TWO STORY SFD.
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | SERGIO MUNIZ |
| Corrections Issued | 4/2/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| Applicant returned to address corrections | 2/22/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/7/2023 | JESSE ARELLANO |
| Plan Check Approved | 3/23/2023 | MOHAMMAD ESMAILI |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 3/3/2025 | JOHN HAYES |
| Permit Finaled | 5/8/2025 | JOHN JANSON |
| CofO Issued | 5/8/2025 | JOHN JANSON |
| Permit Finaled | 5/8/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/26/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2023 | RYAN KIM |
| Grading Pre-Inspection | Cleared | 3/23/2023 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2024 | Corrections Issued | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 5/6/2024 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 5/6/2024 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/6/2024 | Partial Approval | HENRY KIM |
| Sewer | 5/6/2024 | Approved | HENRY KIM |
| Special/Order Compliance | 5/6/2024 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/17/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Rough | 7/17/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 7/17/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | JOHN HAYES |
| Green Building Rough | 8/6/2024 | Approved | JOHN HAYES |
| HVAC-Rough | 8/6/2024 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 8/6/2024 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 8/8/2024 | Corrections Issued | JOHN HAYES |
| Insulation | 8/8/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 8/14/2024 | Approved | SCOTT SOBEL |
| Final | 3/3/2025 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 3/3/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 3/3/2025 | Approved | JOHN HAYES |