9520 W MONTE MAR DR 90035
Certificate Information: 9520 W MONTE MAR DR 90035
- Application / Permit
- 22014-20000-01366
- Plan Check / Job No.
- B22VN04455
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- L- SHAPED IRREGULAR ADDITION ( 21'-7" X 20'-4" AND 4'-11" X 16'-5") TO EX. SFD FOR TWO NEW BEDROOMS, NEW BATHROOM, LIVING ROOM AND ENTRY. INTERIOR REMODEL AND CONVERT EX. BEDROOM TO NEW LIVING ROOM. WORK PER ENGINEER. AUTOMATIC FIRE SPRINKLER REQUIRED.
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofO Issued on 7/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2022 | ROSENDO MEDINA |
| Corrections Issued | 4/2/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 7/8/2022 | ROSENDO MEDINA |
| Plan Check Approved | 7/12/2022 | ROSENDO MEDINA |
| Issued | 7/14/2022 | APPLICANT |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| CofO in Progress | 7/20/2023 | CLAYTON GRAHAM |
| Permit Finaled | 7/26/2023 | DANIEL ORRANTE |
| CofO Issued | 7/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | DINAH GARIN |
| Sewer availability | Cleared | 5/12/2022 | DINAH GARIN |
| ZA Case | Cleared | 6/16/2022 | MAYELA VILLA |
| Roof/Waste drainage to street | Cleared | 6/23/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/12/2022 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 12/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 1/13/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 1/13/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 1/13/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/17/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 2/17/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 2/17/2023 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Rough | 2/17/2023 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/17/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/23/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 2/23/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/27/2023 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | JEREMY TODD |
| Green Building Rough | 3/6/2023 | Approved | JEREMY TODD |
| Shower Pan | 3/10/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/13/2023 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 3/22/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 3/30/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 3/31/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/7/2023 | Approved | ASHLEY THOMPSON |
| Final | 5/31/2023 | Not Ready for Inspection | JEREMY TODD |
| Green Building Final | 5/31/2023 | No Access for Inspection | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Not Required | JEREMY TODD |
| Smoke Detectors | 5/31/2023 | No Access for Inspection | JEREMY TODD |
| ELECTRICAL-Final | 6/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 6/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 6/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 6/9/2023 | Conditional Approval | CLAYTON GRAHAM |
| PLUMBING-Final | 6/9/2023 | Approved | CLAYTON GRAHAM |
| Smoke Detectors | 6/9/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 6/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 6/13/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 6/13/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 6/27/2023 | Approved | CLAYTON GRAHAM |
| Final | 6/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 6/27/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 6/27/2023 | Approved | CLAYTON GRAHAM |
| Final | 7/19/2023 | OK to Issue CofO | CLAYTON GRAHAM |