6370 W 85TH PL 90045
Certificate Information: 6370 W 85TH PL 90045
- Application / Permit
- 22014-20000-01359
- Plan Check / Job No.
- B22VN04434
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION IRREGULAR ( 24' X 26'-4" ) TO (E) SFD FOR NEW BEDROOM/ BATHROOM AND STUDY. REMODEL BATHROOMS, KITCHEN/LIVING ROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | ROSENDO MEDINA |
| Corrections Issued | 3/26/2022 | ROSENDO MEDINA |
| Plan Check Approved | 4/26/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 3/21/2023 | HERBERT GIRON |
| Permit Finaled | 3/24/2023 | DANIEL ORRANTE |
| CofO Issued | 3/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 4/4/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 4/8/2022 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 4/8/2022 | RAYMOND MUGAMBWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2022 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 7/14/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 8/2/2022 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 8/2/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 1/11/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 1/11/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 1/13/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 1/13/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 1/13/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 1/25/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 1/25/2023 | Approved | HERBERT GIRON |
| Wood Frame | 1/25/2023 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2023 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 1/27/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 1/31/2023 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 2/2/2023 | Conditional Approval | HERBERT GIRON |
| Insulation | 2/2/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/7/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 2/9/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/9/2023 | Approved | HERBERT GIRON |
| Shower Pan | 2/9/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/13/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 3/13/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 3/13/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 3/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 3/15/2023 | Corrections Issued | HERBERT GIRON |
| Final | 3/15/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/15/2023 | Approved | HERBERT GIRON |
| Green Building Final | 3/15/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 3/15/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 3/15/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 3/15/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/21/2023 | Approved | HERBERT GIRON |
| Final | 3/21/2023 | OK to Issue CofO | HERBERT GIRON |
| Gas Test | 3/21/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 3/21/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | HERBERT GIRON |