9142 N JELLICO AVE 91325
Certificate Information: 9142 N JELLICO AVE 91325
- Application / Permit
- 22014-20000-01352
- Plan Check / Job No.
- B22VN04402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (18'-6"x22'-2") ADDITION TO EXTEND AND REMODEL THE (E) MASTER BEDROOM, BATHROOM AND CLOSET
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2022 | PETER MOSESIAN |
| Corrections Issued | 3/24/2022 | PETER MOSESIAN |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 5/16/2022 | PETER MOSESIAN |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 6/24/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
| CofO Issued | 7/1/2025 | RUBEN SALAS |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 5/9/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | J L Hahn Construction; Lic. No.: 1004516-B | 17541 W HARRIS WAY #204 CANYON COUNTRY, CA 91387 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 6/21/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/27/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/27/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/27/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/27/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | MATTHEW NELSON |
| Insulation | 8/8/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/8/2023 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 8/16/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 8/16/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/22/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Final | 10/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 10/17/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/17/2023 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 10/17/2023 | Approved | JAVIER RAMOS JR |
| Final | 10/26/2023 | Conditional Approval | ROBERT GOLD |
| Green Building Final | 10/26/2023 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Approved | ROBERT GOLD |
| Final | 6/24/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |