16639-16641 W JERSEY ST 91344

Certificate Information: 16639-16641 W JERSEY ST 91344

Application / Permit
22014-20000-01348
Plan Check / Job No.
B22VN04396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT AND 17'2" X 28'10" IRR. SHAPE ADDITION TO (E) SFD.
Permit Issued
Issued on 8/3/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/22/2022 PINANK PATEL
Corrections Issued 4/23/2022 PINANK PATEL
Building Plans Picked Up 5/2/2022 APPLICANT
Plan Check Approved 7/28/2022 PINANK PATEL
Issued 8/3/2022 APPLICANT
CofO in Progress 9/25/2024 JAVIER RAMOS JR
CofO Issued 10/18/2024 DANIEL ORRANTE
Permit Finaled 10/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/6/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/6/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/8/2022 CARLOS AGUILERA
Sewer availability Cleared 7/8/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/11/2023 Approved JAVIER RAMOS JR
Pre-Inspection 4/11/2023 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/25/2023 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/13/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 6/13/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 6/13/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/13/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/13/2023 Approved JAVIER RAMOS JR
HVAC-Rough 6/15/2023 Approved JAVIER RAMOS JR
Insulation 6/15/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Approved JAVIER RAMOS JR
Insulation 6/30/2023 Partial Approval JAVIER RAMOS JR
Drywall Nailing 7/5/2023 Approved JAVIER RAMOS JR
Insulation 7/5/2023 Approved JAVIER RAMOS JR
Shower Pan 7/17/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/12/2023 Not Ready for Inspection CARLOS MATAMOROS
Final 8/12/2023 Corrections Issued CARLOS MATAMOROS
Green Building Final 8/12/2023 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 8/12/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/12/2023 SGSOV Approved CARLOS MATAMOROS
Service/Power Release 8/12/2023 Approved CARLOS MATAMOROS
Smoke Detectors 8/12/2023 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 8/16/2023 Approved JAVIER RAMOS JR
Final 8/16/2023 Corrections Issued JAVIER RAMOS JR
Gas Test 8/16/2023 Approved JAVIER RAMOS JR
Green Building Final 8/16/2023 Approved JAVIER RAMOS JR
Smoke Detectors 8/16/2023 Approved JAVIER RAMOS JR
Final 9/24/2024 OK to Issue CofO JAVIER RAMOS JR