8488 N GLENOAKS BLVD 91352
Certificate Information: 8488 N GLENOAKS BLVD 91352
- Application / Permit
- 22014-20000-01323
- Plan Check / Job No.
- B22VN04313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION AND 15'5" X 13'7" ADDITION OF ACCESSORY DWELLING UNIT PER LAMC SEC. 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | PINANK PATEL |
| Corrections Issued | 3/26/2022 | PINANK PATEL |
| Plan Check Approved | 7/1/2022 | PINANK PATEL |
| Issued | 7/5/2022 | APPLICANT |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| CofO in Progress | 6/24/2023 | DAVID ANDERSON |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2022 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2022 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 5/18/2022 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 7/3/2022 | TINA MIRANDA |
| Construction within easement | Cleared | 7/3/2022 | TINA MIRANDA |
| Grading Pre-Inspection | Cleared | 7/3/2022 | PINANK PATEL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/5/2022 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/8/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 2/8/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/23/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/23/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/23/2023 | Approved | DAVID ANDERSON |
| Insulation | 2/23/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/7/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 3/15/2023 | Approved | DAVID ANDERSON |
| Sewer | 3/30/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 3/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 4/3/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 4/17/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/24/2023 | Approved | DAVID ANDERSON |
| Final | 6/14/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/14/2023 | Approved | DAVID ANDERSON |
| Green Building Final | 6/14/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 6/14/2023 | Approved | DAVID ANDERSON |
| Final | 6/23/2023 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | DAVID ANDERSON |