6544-6544 1/2 N CLYBOURN AVE 91606

Certificate Information: 6544-6544 1/2 N CLYBOURN AVE 91606

Application / Permit
22014-20000-01321
Plan Check / Job No.
B22VN04305
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) DET GARAGE TO ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c) & (d)] AND ADD A NEW 2ND FLOOR DWELLING UNIT (411 SF) [PER SB9]; NFPA-13D THRU-OUT
Permit Issued
Issued on 12/11/2023
Issuing Office
Current Status
Issued on 12/11/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 TROY DEGUZMAN
Corrections Issued 4/15/2022 TROY DEGUZMAN
Quality Review Completed 4/18/2022 OMID HEDAYAT
Building Plans Picked Up 4/20/2022 APPLICANT
Applicant returned to address corrections 5/26/2022 TROY DEGUZMAN
Applicant returned to address corrections 10/27/2022 SEAN SHAHMIRI
Applicant returned to address corrections 4/10/2023 SEAN SHAHMIRI
Plan Check Approved 11/8/2023 SEAN SHAHMIRI
Issued 12/11/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/21/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/25/2022 JOSE DUARTE-DIAZ
Green Code Cleared 5/26/2022 TROY DEGUZMAN
Hydrant and Access approval Cleared 7/8/2022 KURT CORRAL
Low Impact Development Cleared 10/12/2022 LUIS LUVANO
Senate Bill 9 Cleared 9/28/2023 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 11/8/2023 CARLOS AGUILERA
Sewer availability Cleared 12/1/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/14/2023 Not Ready for Inspection JOHN HAYES
Pre-Inspection 12/18/2023 Corrections Issued DAVID MATSON
Pre-Inspection 3/8/2024 No Access for Inspection MISAEL ESPARZA
Pre-Inspection 4/9/2024 Corrections Issued JOHN HAYES
Pre-Inspection 7/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 7/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 8/2/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/15/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/29/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Partial Approval MISAEL ESPARZA
Sewer 9/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 10/29/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/14/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/14/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/14/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Shower Pan 3/14/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/11/2025 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 5/8/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 6/4/2025 Partial Approval MICHAEL CORTEZ
Rough-Elec/Plmb/HVAC 6/23/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/26/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/29/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 9/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/2/2025 Corrections Issued JOSE AVILA
Pre-Inspection 3/13/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/8/2026 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 6/8/2026 Approved GAREN HAYRAPETYAN
Pre-Inspection 6/8/2026 Partial Inspection GAREN HAYRAPETYAN