4519 N WORTSER AVE 91604

Certificate Information: 4519 N WORTSER AVE 91604

Application / Permit
22014-20000-01315
Plan Check / Job No.
B22VN04294
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION OF 7' X 11'3" OF NEW BATHROOMS AND ROOM SPACE TO THE (E) SFD PER ENGINEER.
Permit Issued
Issued on 8/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 PINANK PATEL
Corrections Issued 3/26/2022 PINANK PATEL
Applicant returned to address corrections 5/6/2022 PINANK PATEL
Applicant returned to address corrections 5/11/2022 PINANK PATEL
Applicant returned to address corrections 6/9/2022 PINANK PATEL
Building Plans Picked Up 6/9/2022 APPLICANT
Plan Check Approved 8/18/2022 OMAR GARNICA
Issued 8/18/2022 APPLICANT
CofO in Progress 3/18/2024 CHRISTOPHE COCHRAN
Permit Finaled 4/10/2024 RUBEN SALAS
CofO Issued 4/10/2024 RUBEN SALAS
Permit Finaled 4/10/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/16/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/29/2022 ABDULLAH SADOZAI
Sewer availability Cleared 7/29/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/30/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/30/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/6/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/31/2023 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 1/31/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Partial Approval JOHN COLEMAN
Deputy Wood Construction 3/16/2023 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 4/10/2023 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/25/2023 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/31/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/31/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 5/31/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 5/31/2023 Approved CHRISTOPHE COCHRAN
Insulation 6/6/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/9/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/26/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 6/26/2023 Approved CHRISTOPHE COCHRAN
Final 3/11/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 3/11/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 3/11/2024 Approved CHRISTOPHE COCHRAN
Final 3/18/2024 OK to Issue CofO CHRISTOPHE COCHRAN