4519 N WORTSER AVE 91604
Certificate Information: 4519 N WORTSER AVE 91604
- Application / Permit
- 22014-20000-01315
- Plan Check / Job No.
- B22VN04294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION OF 7' X 11'3" OF NEW BATHROOMS AND ROOM SPACE TO THE (E) SFD PER ENGINEER.
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | PINANK PATEL |
| Corrections Issued | 3/26/2022 | PINANK PATEL |
| Applicant returned to address corrections | 5/6/2022 | PINANK PATEL |
| Applicant returned to address corrections | 5/11/2022 | PINANK PATEL |
| Applicant returned to address corrections | 6/9/2022 | PINANK PATEL |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Plan Check Approved | 8/18/2022 | OMAR GARNICA |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 3/18/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/16/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2022 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 7/29/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/30/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/30/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/6/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Partial Approval | JOHN COLEMAN |
| Deputy Wood Construction | 3/16/2023 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 4/10/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/25/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/31/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/31/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/9/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/26/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 6/26/2023 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/11/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 3/11/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/11/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/18/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |