6041 N BELLINGHAM AVE 91606
Certificate Information: 6041 N BELLINGHAM AVE 91606
- Application / Permit
- 22014-20000-01312
- Plan Check / Job No.
- B22VN04288
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 7' X 6' DINING ROOM ADDITION TO (E) SFD ,RE-FRAME PORTION OF THE ROOF, ALL WORK PER ENGINEERING "COMPLY WITH DEPARTMENT ORDER effective date 06/17/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 3/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2022 | RARES BODEA |
| Corrections Issued | 3/30/2022 | RARES BODEA |
| Applicant returned to address corrections | 4/11/2022 | RARES BODEA |
| Plan Check Approved | 4/12/2022 | RARES BODEA |
| Issued | 4/13/2022 | APPLICANT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| Permit Finaled | 3/27/2024 | DANIEL ORRANTE |
| CofO Issued | 3/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/2/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 5/16/2022 | Corrections Issued | MATT KELLERMAN |
| BUILDING-Rough-Frame | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/2/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Final | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Rough | 2/2/2023 | Approved | KIRK SANDERS |
| Smoke Detectors | 2/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 2/15/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/26/2024 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 3/26/2024 | Approved | JUAN VALENZUELA |
| Final | 3/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/26/2024 | Approved | JUAN VALENZUELA |
| Green Building Final | 3/26/2024 | Approved | JUAN VALENZUELA |
| Green Building Rough | 3/26/2024 | Approved | JUAN VALENZUELA |
| MERV13>=Final | 3/26/2024 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 3/26/2024 | Approved | JUAN VALENZUELA |