8025 N BELLINGHAM AVE 91605
Certificate Information: 8025 N BELLINGHAM AVE 91605
- Application / Permit
- 22014-20000-01310
- Plan Check / Job No.
- B22VN04282
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 834SF ADDITION TO (E) ONE STORY SFD _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | DAWN MC NULTY |
| Corrections Issued | 4/21/2022 | DAWN MC NULTY |
| Quality Review Completed | 4/26/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 8/24/2022 | DAWN MC NULTY |
| Issued | 8/30/2022 | APPLICANT |
| CofO in Progress | 3/21/2023 | MATTHEW NELSON |
| CofO Issued | 4/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/26/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 6/3/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 6/6/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2022 | No Result Entered | ADRIAN GAUTHIER |
| Footing/Foundation/Slab | 9/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Reinf. Concrete | 9/29/2022 | No Result Entered | ADRIAN GAUTHIER |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 10/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 10/25/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Wood Frame | 10/25/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/15/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/15/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 12/15/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/15/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 12/15/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/21/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 12/21/2022 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | MATTHEW NELSON |
| Insulation | 1/5/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/5/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 1/5/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/10/2023 | Approved | MATTHEW NELSON |
| Underground Mechanical | 2/6/2023 | Approved | MATTHEW NELSON |
| Final | 3/20/2023 | OK to Issue CofO | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/20/2023 | Approved | MATTHEW NELSON |
| Green Building Final | 3/20/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/20/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/20/2023 | Approved | MATTHEW NELSON |