4947 N SYCAMORE TER 90042

Certificate Information: 4947 N SYCAMORE TER 90042

Application / Permit
22014-20000-01301
Plan Check / Job No.
B22VN04256
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL TO (E) 2-STORY DUPLEX (INCLUDED PORCH), NEW GROUND LEVEL DECK FOR 1ST FLOOR UNIT . Extend and Convert (E) deteched garage to carport
Permit Issued
Issued on 2/16/2023
Issuing Office
Current Status
Permit Finaled on 8/21/2024

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 JAD BASMA
Corrections Issued 4/22/2022 JAD BASMA
Quality Review Completed 4/27/2022 KEN GILL
Building Plans Picked Up 5/4/2022 APPLICANT
Applicant returned to address corrections 7/20/2022 JAD BASMA
Plan Check Approved 8/5/2022 JAD BASMA
Issued 2/16/2023 APPLICANT
Permit Finaled 6/14/2024 OSVALDO PARAMO
CofO in Progress 7/5/2024 OSVALDO PARAMO
No Progress 7/9/2024 CHARLES BOGHOSKHAN
CofO in Progress 7/9/2024 CHARLES BOGHOSKHAN

Permit Application Clearance Information

HPOZ Cleared 6/22/2022 KATIE DEBIASE
Eng Process Fee Ord 176,300 Cleared 6/27/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 6/27/2022 JEANIE LAM
Sewer availability Cleared 6/27/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/6/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 6/6/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/13/2023 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 7/7/2023 Approved RUBEN SALAS
ELECTRICAL-Rough 7/17/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 7/20/2023 Approved OSVALDO PARAMO
Shower Pan 7/27/2023 Approved BRENDAN MORELLI
Shower Pan 8/3/2023 Approved JOSH MEISTER
HVAC-Rough 9/12/2023 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 10/13/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval OSVALDO PARAMO
Green Building Rough 10/13/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/13/2023 Partial Approval OSVALDO PARAMO
Wood Frame 10/13/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 11/13/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 11/13/2023 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 11/13/2023 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 11/28/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Conditional Approval OSVALDO PARAMO
HVAC-Rough 11/28/2023 Corrections Issued OSVALDO PARAMO
Interior/Exterior Lathing 11/28/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/6/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/6/2023 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 12/6/2023 Approved ALIZAH MAYAGOITIA
Insulation 12/8/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 12/15/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 2/23/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 5/14/2024 Corrections Issued OSVALDO PARAMO
Gas Test 5/14/2024 Approved OSVALDO PARAMO
PLUMBING-Final 5/14/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 5/14/2024 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 5/28/2024 Approved OSVALDO PARAMO
Final 5/28/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/28/2024 Approved OSVALDO PARAMO
Green Building Final 5/28/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 5/28/2024 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 5/28/2024 Approved OSVALDO PARAMO
Final 6/12/2024 Partial Inspection OSVALDO PARAMO
Service/Power Release 6/12/2024 Approved OSVALDO PARAMO
Final 6/14/2024 Permit Finaled OSVALDO PARAMO