17525 W KITTRIDGE ST 91406
Certificate Information: 17525 W KITTRIDGE ST 91406
- Application / Permit
- 22014-20000-01300
- Plan Check / Job No.
- B22VN04253
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d), AND AN ADDITION OF 16' x 19'4". DESIGN PER WFPP.
- Permit Issued
- Issued on 9/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | LUIS RINCON |
| Corrections Issued | 3/26/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/5/2022 | APPLICANT |
| Plan Check Approved | 9/23/2022 | JOSEPH RAFOLS |
| Issued | 9/26/2022 | APPLICANT |
| CofO in Progress | 5/23/2023 | JON MCHUGH |
| Permit Finaled | 5/23/2023 | JOHN JANSON |
| CofO Issued | 5/23/2023 | JOHN JANSON |
| Permit Finaled | 5/23/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/5/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/20/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/20/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/1/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 12/1/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 12/8/2022 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 12/8/2022 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 1/31/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 1/31/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 1/31/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 1/31/2023 | Approved | JON MCHUGH |
| Wood Frame | 1/31/2023 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 2/10/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 2/13/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 2/13/2023 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 2/13/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 2/13/2023 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 2/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 2/14/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 2/15/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 2/15/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 2/15/2023 | Approved | SEAN HAUPT |
| Insulation | 2/15/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 2/15/2023 | Approved | SEAN HAUPT |
| Shower Pan | 2/15/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 2/16/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/17/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 3/17/2023 | Approved | JON MCHUGH |
| Final | 5/2/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/2/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 5/2/2023 | Approved | JON MCHUGH |
| Pre-Inspection | 5/4/2023 | Not Ready for Inspection | SEAN HAUPT |
| Final | 5/8/2023 | Partial Approval | JON MCHUGH |