11350 N TAMARACK AVE 91340

Certificate Information: 11350 N TAMARACK AVE 91340

Application / Permit
22014-20000-01274
Plan Check / Job No.
B22VN04191
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 16'-5" X 22'-5" DETACHED GARAGE WITH (N) 25'-11" X 35'-8" IRREGULAR SHAPED ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 9/21/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2022 APPLICANT
Corrections Issued 3/22/2022 JESSE ARELLANO
Assigned to Plan Check Engineer 3/23/2022 JESSE ARELLANO
Building Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 9/1/2022 ALEC MOUSAKHANIAN
Issued 9/21/2022 APPLICANT
CofO in Progress 3/5/2025 JENNIFER RABUCHIN
Permit Finaled 3/15/2025 RUBEN SALAS
CofO Issued 3/15/2025 RUBEN SALAS
Permit Finaled 3/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/11/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/11/2022 LEE GUILBEAUX
Sewer availability Cleared 4/11/2022 LEE GUILBEAUX
Construction near power lines Cleared 6/3/2022 RIDWAN HARDY
Low Impact Development Cleared 8/3/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/17/2022 MEGAN GODINEZ
Green Code Cleared 9/1/2022 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/1/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/22/2022 Partial Inspection JENNIFER RABUCHIN
Sewer 12/22/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/5/2023 Partial Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 1/11/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/2/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 3/2/2023 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Approval JENNIFER RABUCHIN
Wood Frame 3/10/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/28/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/28/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 3/28/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 3/28/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 4/3/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/3/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/3/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/10/2023 Partial Approval JENNIFER RABUCHIN
Insulation 4/14/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 4/18/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/21/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/21/2025 Corrections Issued JENNIFER RABUCHIN
Final 2/21/2025 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 2/21/2025 Partial Approval JENNIFER RABUCHIN
Green Building Final 2/21/2025 Approved JENNIFER RABUCHIN
Green Building Rough 2/21/2025 Approved JENNIFER RABUCHIN
HVAC-Final 2/21/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/21/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/21/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/25/2025 Approved JENNIFER RABUCHIN
Final 2/25/2025 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 2/25/2025 Approved JENNIFER RABUCHIN
HVAC-Final 2/25/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/25/2025 Approved JENNIFER RABUCHIN
Service/Power Release 3/5/2025 Approved JENNIFER RABUCHIN