6546 N BABCOCK AVE 91606
Certificate Information: 6546 N BABCOCK AVE 91606
- Application / Permit
- 22014-20000-01263
- Plan Check / Job No.
- B22VN04171
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE. ***SHALL BE SPRINKLERED PER NFPA 13 D***
- Permit Issued
- Issued on 5/30/2022
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/21/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/18/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/11/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 5/24/2022 | MICHAEL LOPEZ |
| Issued | 5/30/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | KIRK SANDERS |
| CofO Issued | 8/8/2023 | RUBEN SALAS |
| Permit Finaled | 8/8/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 4/14/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/15/2022 | ROMAN GUTIERREZ |
| Construction within easement | Cleared | 5/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/12/2022 | Partial Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 9/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/19/2022 | Approved | ALAN MORELOS |
| Gas Test | 9/19/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 9/19/2022 | Partial Approval | ALAN MORELOS |
| Sewer | 9/19/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 9/19/2022 | Partial Approval | ALAN MORELOS |
| ELECTRICAL-Rough | 10/21/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/21/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 10/27/2022 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 10/27/2022 | Approved | CALEB MEISTER |
| Wood Frame | 10/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 12/28/2022 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 12/28/2022 | Approved | KIRK SANDERS |
| HVAC-Rough | 12/28/2022 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 12/28/2022 | Approved | KIRK SANDERS |
| Wood Frame | 12/28/2022 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 1/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/26/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 1/31/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/2/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 2/17/2023 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 2/17/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 2/24/2023 | Approved | KIRK SANDERS |
| Insulation | 2/24/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 3/1/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/28/2023 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 3/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 7/3/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 7/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 7/3/2023 | Approved | KIRK SANDERS |
| Final | 7/11/2023 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 7/11/2023 | Approved | KIRK SANDERS |
| Service/Power Release | 7/11/2023 | Approved | KIRK SANDERS |