23715-23717 W HAYNES ST 91307
Certificate Information: 23715-23717 W HAYNES ST 91307
- Application / Permit
- 22014-20000-01260
- Plan Check / Job No.
- B22VN04170
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE AND PART OF SFD TO ADU. (TOTAL ADU FLOOR AREA 639.5 SF)
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- Issued on 4/5/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2022 | JOE VO |
| Corrections Issued | 3/21/2022 | JOE VO |
| Plan Check Approved | 4/5/2022 | JOE VO |
| Issued | 4/5/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: NA64144 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2022 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 6/9/2022 | Approved | TROY SANDERS |
| Deputy Reinf. Concrete | 6/10/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 6/21/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 7/6/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 7/6/2022 | Approved | TROY SANDERS |
| Green Building Rough | 7/6/2022 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 7/6/2022 | Approved | TROY SANDERS |
| Insulation | 7/19/2022 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | JESUS PINEDA |
| Insulation | 7/21/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/9/2022 | Approved | JESUS PINEDA |
| Green Building Rough | 8/9/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/18/2022 | Approved | JESUS PINEDA |
| Shower Pan | 8/18/2022 | Approved | JESUS PINEDA |
| Final | 9/22/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/22/2022 | Approved | TROY SANDERS |