- 4'-3" X 5'-11" FRONT ADDITION TO SINGLE FAMILY DWELLING (25 SF), 6'-6" X 11'-0" & 19'-0" X 11'-0" ADDITION TO AND CONVERT THE (E) ONE CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT (489 SF) PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/2/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 3/29/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 7/12/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Issued | 9/2/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 4/1/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/1/2022 | DAGOVERTO GUERRERO |
Contact Information
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/3/2022 | Partial Approval | WILLIAM WREN |
| Sewer | 11/3/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 11/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Special/Order Compliance | 11/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/6/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 12/27/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/23/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 1/23/2023 | Corrections Issued | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 1/27/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/31/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/31/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/31/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 1/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 1/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 3/9/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/28/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 4/28/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/28/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/3/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 5/3/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/12/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/12/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | No Access for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/29/2023 | No Access for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 6/30/2023 | Approved | MATTHEW NELSON |
| Insulation | 7/20/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/1/2023 | Partial Approval | GREGG CUMMINGS |
| Insulation | 8/1/2023 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 8/8/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 8/8/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 8/23/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 8/29/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 8/29/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/19/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| MERV13>=Final | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/26/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/26/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/5/2024 | Corrections Issued | VINCENT HANLEY |
| Final | 6/5/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/5/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/5/2024 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Final | 6/5/2024 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 6/5/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/11/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/28/2024 | Approved | VINCENT HANLEY |
| Final | 6/28/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/28/2024 | Approved | VINCENT HANLEY |
| MERV13>=Final | 6/28/2024 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 6/28/2024 | Approved | VINCENT HANLEY |