10855 N FELLOWS AVE 91331

Certificate Information: 10855 N FELLOWS AVE 91331

Application / Permit
22014-20000-01245
Plan Check / Job No.
B22VN04111
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ATTACHED GARAGE, CONVERT (E) GARAGE TO LIVING AREA, ADDITION AND REMODEL TO (E) SFD
Permit Issued
Issued on 5/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 SELLA BENYAMIN
Corrections Issued 4/28/2022 SELLA BENYAMIN
Building Plans Picked Up 9/15/2022 APPLICANT
Quality Review Completed 12/1/2022 SELLA BENYAMIN
Plan Check Approved 12/1/2022 SELLA BENYAMIN
Issued 5/16/2023 APPLICANT
CofO in Progress 5/22/2025 MICHEL ABAJAN
Permit Finaled 5/23/2025 RUBEN SALAS
CofO Issued 5/23/2025 RUBEN SALAS
Permit Finaled 5/23/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/25/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/25/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/25/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/25/2022 CARLOS AGUILERA
Hold Cleared 10/25/2022 MARIA VENDIVIL
Roof/Waste drainage to street Cleared 10/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/26/2022 CARLOS AGUILERA
Sewer availability Cleared 10/26/2022 CARLOS AGUILERA
Permit Cleared 11/8/2022 CARLOS AGUILERA
Trees in Parkway Cleared 11/8/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/18/2023 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 6/9/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/12/2023 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 6/13/2023 Conditional Approval ROBERT GOLD
PLUMBING-Rough 7/17/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 8/1/2023 Approved MICHEL ABAJAN
Gas Test 8/11/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/30/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 8/30/2023 Approved MICHEL ABAJAN
Green Building Rough 8/30/2023 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/8/2023 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 9/8/2023 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/10/2023 Approved MICHEL ABAJAN
Green Building Rough 10/10/2023 Approved MICHEL ABAJAN
Insulation 10/19/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/19/2023 Approved MICHEL ABAJAN
Drywall Nailing 10/31/2023 Approved MISAEL ESPARZA
Shower Pan 10/31/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/3/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 1/2/2025 Approved MICHEL ABAJAN
Final 1/2/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 1/2/2025 Approved MICHEL ABAJAN
HVAC-Final 1/2/2025 Approved MICHEL ABAJAN
PLUMBING-Final 1/2/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/2/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/23/2025 Approved MICHEL ABAJAN
Final 2/21/2025 Corrections Issued MICHEL ABAJAN
Final 5/21/2025 OK to Issue CofO MICHEL ABAJAN